PROJECTS

Throughout our nearly five decades of experience in heavy lift and transport solutions, we have learned that a successful job is built on precise planning and safe execution. This mindset has allowed our business to grow and positively impact some of the most complex projects across two continents. Take a look at what we can do.

Pressed for Time

View Project
Pressed for Time

A vehicle manufacturer’s large stamping press—a massive machine used for shaping body panels—is online and operational thanks to efficient installation by Deep South. The three primary components included a 181-ton press bed (27.72’ L x 16.4’ W x 13.12’ H), 250-ton press crown (28.38’ L x 16.4’ W x 13.12’ H) and a 92-ton press slide (21’ x 10.83’ x 10.5’).

Saddle Up: Customized Solutions Place Refinery Column with Care

View Project
Saddle Up: Customized Solutions Place Refinery Column with Care

The Deep South team was tasked to receive, transport and set a 790,025-pound debutanizer. This specialized distillation column measures 174’-3” long with a 21’-3” diameter. The debutanizer was received from an ocean-going vessel at the Port of New Orleans. Once cleared through customs, the debutanizer was loaded on a barge and pushed to a roll-off site 8 hours upriver, and prepared for transport to the refinery.

An Award Winning Multi-Scope Lift and Set

View Project
An Award Winning Multi-Scope Lift and Set

As part of a petrochemical facility expansion in Texas, the client needed more than 60 pieces of equipment of various weights and sizes moved and placed in tight confines—in just four months. With very little room for errors or delays, and no time to spare, Deep South’s skilled engineers and managers put together an impressive engineering plan to facilitate a safe and efficient effort.

Facilitating a Refinery Column Placement in Tight Confines

View Project
Facilitating a Refinery Column Placement in Tight Confines

Transporting, placing, and lifting a refinery column — one that is comparable to the height and weight of the Statue of Liberty — is a familiar challenge for heavy lift, heavy haul experts like Deep South. Maneuvering it around existing racks and systems adds another layer of complexity.

Haul & Lift of Refinery Combination Tower Goes Off Without a Hitch

View Project
Haul & Lift of Refinery Combination Tower Goes Off Without a Hitch

Load, haul, roll and set — seemingly simple words unless associated with a 555,000-pound, 160-foot long, 18-foot wide, over 19-foot tall refinery combination tower.

Transporters and Cranes Facilitate Processing Plant Upgrade

View Project
Transporters and Cranes Facilitate Processing Plant Upgrade

The movement and replacement of process plant components are a familiar site in in the Texas Gulf Coast region—though not often to the scale and timeline faced by one EPC contractor. Per the client, the contractor was tasked with the haul and lift of two trains of fractionation tower components (debutanizer, depropanizer, splitter and deethanizer) over the course of nine months.

Many Lifts, One Solution: Modular Lift System Flexes Hydraulic Muscles During Process Plant Overhaul

View Project
Many Lifts, One Solution: Modular Lift System Flexes Hydraulic Muscles During Process Plant Overhaul

Deep South crews were challenged to haul, lift, and set 84 modules, including three towers (one measuring 100’ long, 350,000 lbs.) as well as various pieces of process equipment, such as piping, tanks, PDC buildings, and transformers—all within a tight schedule. Many of the modules had offset centers of gravity further complicating the lift and set.

Seamless Reactor Haul & Lift Keeps Refinery Upgrade on Track

View Project
Seamless Reactor Haul & Lift Keeps Refinery Upgrade on Track

In St. Charles Parish, LA, Deep South Crane & Rigging completed a massive vessel transport and lift project in support of a major refinery upgrade.

Turnaround Efficiency: Lift, Lower and Slide

View Project
Turnaround Efficiency: Lift, Lower and Slide

A major process unit turnaround (TAR) project for a petrochemical plant in the Southwest required some well-planned logistics, over 1,200 craftworkers (at peak) and a comprehensive fleet of cranes, trucks and customized skid (Jack & Slide) systems.

Go Small to Gain Big: Transport Optimized for Efficient Transport

View Project
Go Small to Gain Big: Transport Optimized for Efficient Transport

When an oil & gas customer needed help transporting a new oxygen tank from Texas to a gas facility in South Carolina, the options seemed costly and complex. Deep South’s logistics specialists took a custom approach to the transport of a 375,000-lb oxygen tank from road to rail to plant, saving time and money for the client.

Bridge Span Transportation

Bridge Span Move and Lift Set Pace for New Bridge Completion

View Project
Bridge Span Move and Lift Set Pace for New Bridge Completion

In support of a major bridge construction project in the Midwest, Deep South crews helped transport and install four bridge spans from an off-site staging area to the bridge foundation.

Custom Connections Deliver Heavy Systems Safely, Timely, and Cost Effectively

View Project
Custom Connections Deliver Heavy Systems Safely, Timely, and Cost Effectively

Deep South has put its transport and skills to work for a heavy industrial project in the Southwest that required Deep South to direct discharge from ships gear to barge, haul and sett a cold box, depropanizer and six modules.

Turnkey in Tight Quarters

Turnkey in Tight Quarters: Split Trailers Reduce Height with Inches to Spare

View Project
Turnkey in Tight Quarters: Split Trailers Reduce Height with Inches to Spare

For a refinery in the Southeast, Deep South was contracted to remove and replace a derrick structure and two 491,000-pound vessels, each measuring 99’ long and 24’2” diameter.

Chemical Reactor Transport

124-line SPMT Chemical Reactor Transport

View Project
124-line SPMT Chemical Reactor Transport

In the Southwest, Deep South received three vessels from a heavy lift ship at the Port of Houston, barged the vessels, and transported them to final staging using a total of 124-axle lines Scheuerle SPMT. The heaviest vessel weighed 1,800,000 pounds and the total gross weight at transport for that vessel was 2,300,000 pounds.

heavy lift system

Combined Gantry/Strand Jack Systems Power Lifts Co-Gen Train

View Project
Combined Gantry/Strand Jack Systems Power Lifts Co-Gen Train

The construction of a combined-cycle power station in Louisiana required a specialty contractor to move, lift and set a STG generator (692,250 lbs.) and HIP turbine (392,420 lbs.).

Heavy lift tail crane

Tailing Over a Live Pipe Rack Emphasizes Complex Project

View Project
Tailing Over a Live Pipe Rack Emphasizes Complex Project

From a tricky bridge crossing to a complex coordinated lift, Deep South facilitated the delivery and setting of components for a petrochemical facility acid modification and upgrade project in Louisiana. The key components included a 627,000-pound acid settler, 689,000-pound first stage reactor, acid storage drums and associated parts.

heavy transporter

Bridge Limits: Deep South Facilitates Complex Multi-Stages Delivery of Million Pound Converter

View Project
Bridge Limits: Deep South Facilitates Complex Multi-Stages Delivery of Million Pound Converter

In preparation for a capacity expansion project, Deep South transported a 939,327-pound ammonia converter shell from the manufacturer to its plant in Donaldsonville, La. The trek required moving the system about 135 miles by water to a barge unloading site and 30 miles over the road.

Scheuerles Haul 750 Ton Tugboat

View Project
Scheuerles Haul 750 Ton Tugboat

Deep South was contracted to transport a 750-ton tugboat.

Pressure Valve Transportation Service

Barging Through: Delivering Over 300 Tons of Vessels

View Project
Barging Through: Delivering Over 300 Tons of Vessels

Deep South was contracted to barge and transport cold boxes, pressure vessels, and bullet tanks weighing in at nearly 400 tons.

4 Drum Coker Unit

View Project
4 Drum Coker Unit

Deep South was contracted to complete a full replacement of a four-drum coker unit.

turnkey lift and transport

Gulf Coast Turnkey Transport and Lift of Four Towers

View Project
Gulf Coast Turnkey Transport and Lift of Four Towers

Deep South was contracted to provide turnkey services that included: transport, barging, and setting four towers.

reactor lift and transport

Extreme Circumstances Call for Extreme Measures: A Narrow Canal Requires a Side Roll-Off

View Project
Extreme Circumstances Call for Extreme Measures: A Narrow Canal Requires a Side Roll-Off

Deep South was contracted to deliver a 750,000-pound reactor to a refinery in northern Illinois. The navigable waterway, a highly-trafficked 125-foot wide canal, required a side roll-off.

caustic tower lift

Caustic & PreFrac Tower Lift

View Project
Caustic & PreFrac Tower Lift

Deep South Crane and Rigging was recently contracted by a southeast petrochemical plant as part of a major pre-turnaround project. In order to de-bottleneck ethylene production, Deep South erected a caustic tower and a prefrac tower.

SPMT Project Deep South

Blue Sea Modular Transport

View Project
Blue Sea Modular Transport

In South Carolina, Deep South was contracted to transport and secure seven modules from the fabricator shop to a barge site via Scheuerle SPMTs.

Turnkey Demolition Facilitates Clean Refinery Modernization

View Project
Turnkey Demolition Facilitates Clean Refinery Modernization

In South America, Deep South demolished and removed three units within a petrochemical facility that was more than 50 years old.

Vessel Heavy Haul

37 Vessel Heavy Haul

View Project
37 Vessel Heavy Haul

As part of an expansion project in the Southwest, Deep South received, barged, and transported 37 vessels to complete this project.

Deep South Cranes

400,400 Pound Boiler Lifts

View Project
400,400 Pound Boiler Lifts

Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system and then trans-loaded onto Scheuerle SPMTs in a very congested unit.

Offshore Platform Heavy Transport Services

92-line Offshore Platform Specialty Transport

View Project
92-line Offshore Platform Specialty Transport

Using 92 lines of Scheuerle SPMTs with 3 power pack units, Deep South successfully assisted the client in moving this offshore platform in Texas.

Heavy Transport Using Fabricated Barge Ramp

Mitigating the Mississippi

View Project
Mitigating the Mississippi

Pulling from its resources and years of experience, Deep South designed and fabricated a barge ramp in 2 weeks time meeting the new CORPS requirements and allowing the project to continue on schedule.

A Marathon Job, Literally

View Project
A Marathon Job, Literally

As seen in American Cranes and Transport Magazine

Transforming a 200-acre sugarcane field in Garyville, LA into a state-of-the-art refinery required a $3.8 billion investment and the work of a cadre of contractors with expertise that spanned the entire spectrum of engineering, construction, and rigging. Construction on the Marathon GME project started in March of 2007, and by December of 2009 the refinery was mechanically complete.

A successful job is built on precise planning and safe execution. request a quote