Turnkey Demolition Facilitates Clean Refinery Modernization
The Reficar refinery, first constructed in 1956 in Cartagena, Columbia, was undergoing a clean energy modernization and expansion to more than double its capacity 80,000 barrels per day (bpd) to 165,000 bpd. The refinery is owned and operated by Refinería de Cartagena (REFICAR), an affiliate of Ecopetrol. The overall project includes the construction of a new refinery adjacent to REFICAR's refinery in Cartagena; revamping the existing 80,000 barrel per day refinery; and relief of the regional refining constraints that will enable REFICAR to produce clean, ultra-low sulfur gasoline and diesel from heavy crude.
REFICAR contracted Deep South to complete the safe removal, demolition, and transport of old systems in parallel with the modernization effort. The removal and demolition included a fluid catalytic cracking (FCC) unit, air blower unit, much of the polymerization unit as well as a range of exchangers, and other related systems.
“The demolition of an over 50-year-old plant on a time sensitive schedule required considerable planning and reliable, versatile equipment,” explains Fernando Gonzalez, project engineer with Deep South Crane. “The systems were large, heavy, dirty, and rusty. Every major component had to be broken down into transportable pieces. As always, crew safety was our first priority.”
The FCC unit proved particularly challenging as the complete unit was nearly 200 feet tall, 70 feet wide, and had a total equipment weight of approximately 2,170,000 pounds. Crews cut the reactor into multiple sections and then used Deep South’s patented VersaCrane™ TC-24000, a 1,500-ton compact crane designed for heavy lifts crowded and congested areas, to transport the pieces to the nearby laydown yard.
Over the course of 8 months, Deep South’s crews and local labor performed more than 100 lifts, 50 of which were critical, with the TC-24000 and other cranes including the 750-ton VersaCrane CC-9600 and the 330-ton Demag CC-1800 crawler crane.
The facility equipment removed ranged from exchangers as small as 5,000 pounds to the largest part of the reactor weighing approximately 250,000 pounds.
The Reficar refinery expansion project was commissioned in 2015.
-
Equipment Used
-
Services Used
-
By the Numbers
- Demolished and Removed 3 Units
- 50 Critical Lifts
- 100+ Total Lifts
- Weights Lifted Ranged From 5,000 - 250,000 pounds
Related Projects
124-line SPMT Chemical Reactor Transport
View Project
124-line SPMT Chemical Reactor Transport
In the Southwest, Deep South received three vessels from a heavy lift ship at the Port of Houston, barged the vessels, and transported them to final staging using a total of 124-axle lines Scheuerle SPMT. The heaviest vessel weighed 1,800,000 pounds and the total gross weight at transport for that vessel was 2,300,000 pounds.
Mitigating the Mississippi
View Project
Mitigating the Mississippi
Pulling from its resources and years of experience, Deep South designed and fabricated a barge ramp in 2 weeks time meeting the new CORPS requirements and allowing the project to continue on schedule.
A Marathon Job, Literally
View Project
A Marathon Job, Literally
As seen in American Cranes and Transport Magazine
Transforming a 200-acre sugarcane field in Garyville, LA into a state-of-the-art refinery required a $3.8 billion investment and the work of a cadre of contractors with expertise that spanned the entire spectrum of engineering, construction, and rigging. Construction on the Marathon GME project started in March of 2007, and by December of 2009 the refinery was mechanically complete.