400,400 Pound Boiler Lifts
Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system that was setup outside of the plant. The boilers were lifted and trans-loaded onto 12-line double-wide Scheuerle SPMTs and transported into the Southwest petrochemical refinery through a very congested unit.
Deep South then set them onto their foundations using two 500-ton Liebherr LTM 1400-7.1s and a 265-ton Liebherr LTM 1220-5.1. Each boiler weighed 400,400 pounds and was 52’ long, 13’ wide, and 26’ high.
-
Equipment Used
-
Services Used
-
By the Numbers
- 3 Boilers weighing 400,400 lbs
- Measuring 52’ x 13’ x 26’
Related Projects
Power Move: Transformer Lift and Staging Rises to the Occasion
View Project
Power Move: Transformer Lift and Staging Rises to the Occasion
In support of a power plant project in the Northeast, Deep South crews were tasked with transporting and staging four transformers, each 22’ high, 12’ wide and 14’ long and weighing 314,000 pounds.
Caustic & PreFrac Tower Lift
View Project
Caustic & PreFrac Tower Lift
Deep South Crane and Rigging was recently contracted by a southeast petrochemical plant as part of a major pre-turnaround project. In order to de-bottleneck ethylene production, Deep South erected a caustic tower and a prefrac tower.
300T Offshore Living Quarters Lift
View Project
300T Offshore Living Quarters Lift
This 300T living quarters module was installed onto an offshore support ship using the Terex Demag CC-2800.