400,400 Pound Boiler Lifts
Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system that was setup outside of the plant. The boilers were lifted and trans-loaded onto 12-line double-wide Scheuerle SPMTs and transported into the Southwest petrochemical refinery through a very congested unit.
Deep South then set them onto their foundations using two 500-ton Liebherr LTM 1400-7.1s and a 265-ton Liebherr LTM 1220-5.1. Each boiler weighed 400,400 pounds and was 52’ long, 13’ wide, and 26’ high.
-
Equipment Used
-
Services Used
-
By the Numbers
- 3 Boilers weighing 400,400 lbs
- Measuring 52’ x 13’ x 26’
Related Projects
Beating the Turnaround Clock
View Project
Beating the Turnaround Clock
In the Southwest, a recent turnaround project presented a difficult set of challenges. Crews needed to replace several large pieces of equipment
Big Lift & Logistics
View Project
Big Lift & Logistics
From coordinating barge and road transportation to a heavy lift in a tight space, this project for a heavy industry customer provided the Deep South team an opportunity to show off its capabilities.
37 Vessel Heavy Haul
View Project
37 Vessel Heavy Haul
As part of an expansion project in the Southwest, Deep South received, barged, and transported 37 vessels to complete this project.