400,400 Pound Boiler Lifts
Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system that was setup outside of the plant. The boilers were lifted and trans-loaded onto 12-line double-wide Scheuerle SPMTs and transported into the Southwest petrochemical refinery through a very congested unit.
Deep South then set them onto their foundations using two 500-ton Liebherr LTM 1400-7.1s and a 265-ton Liebherr LTM 1220-5.1. Each boiler weighed 400,400 pounds and was 52’ long, 13’ wide, and 26’ high.
-
Equipment Used
-
Services Used
-
By the Numbers
- 3 Boilers weighing 400,400 lbs
- Measuring 52’ x 13’ x 26’
Related Projects
A Flare for Efficiency
View Project
A Flare for Efficiency
Routine maintenance plant turnarounds are typically anything but straightforward—as a turnaround in the Southeast quickly demonstrated. The effort called for the removal and replacement of three exchangers, as well as a flare modular replacement. The size and location of the exchangers, the tight window for replacement of the flare, and localized high working-wind speeds were a few of the top challenges that the Deep South team were tasked to overcome.
Dismantling and Relocating A Petrochemical Facility
View Project
Dismantling and Relocating A Petrochemical Facility
Deep South was contracted to dismantle and relocate 9 vessels from a petrochemical plant using a combination of barging, heavy transport, and heavy lift services.
Making the Grade - A Steep Bridge Requires Deep South to Power Up
View Project
Making the Grade - A Steep Bridge Requires Deep South to Power Up
Deep South loaded, secured, and transported four pressure vessels from a fabrication shop to a petrochemical facility using a combination of Scheuerle SPMTs, a 500-ton hydraulic gantry, and Goldhofer Dual Lane trailers.