400,400 Pound Boiler Lifts
Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system that was setup outside of the plant. The boilers were lifted and trans-loaded onto 12-line double-wide Scheuerle SPMTs and transported into the Southwest petrochemical refinery through a very congested unit.
Deep South then set them onto their foundations using two 500-ton Liebherr LTM 1400-7.1s and a 265-ton Liebherr LTM 1220-5.1. Each boiler weighed 400,400 pounds and was 52’ long, 13’ wide, and 26’ high.
-
Equipment Used
-
Services Used
-
By the Numbers
- 3 Boilers weighing 400,400 lbs
- Measuring 52’ x 13’ x 26’
Related Projects
Multi-Piece Polypropylene System on the Move
View Project
Multi-Piece Polypropylene System on the Move
A new polypropylene recycling plant in Ohio required a multi-stage transport and lift of multiple modules, process equipment vessels, and various components such as shredders/filters, extruders and candle filters.
Lifting the Dome
View Project
Lifting the Dome
Using the 660-ton Demag CC-2800-1, Deep South successfully set this 244’ in diameter geodesic dome weighing approximately 145,000 pounds.
Making the Grade - A Steep Bridge Requires Deep South to Power Up
View Project
Making the Grade - A Steep Bridge Requires Deep South to Power Up
Deep South loaded, secured, and transported four pressure vessels from a fabrication shop to a petrochemical facility using a combination of Scheuerle SPMTs, a 500-ton hydraulic gantry, and Goldhofer Dual Lane trailers.