400,400 Pound Boiler Lifts

Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system that was setup outside of the plant. The boilers were lifted and trans-loaded onto 12-line double-wide Scheuerle SPMTs and transported into the Southwest petrochemical refinery through a very congested unit. 

Deep South then set them onto their foundations using two 500-ton Liebherr LTM 1400-7.1s and a 265-ton Liebherr LTM 1220-5.1. Each boiler weighed 400,400 pounds and was 52’ long, 13’ wide, and 26’ high. 

  • Equipment Used

    • Hydraulic Gantries
    • Scheuerle SPMT
    • Liebherr LTM 1220-5.1/5.2
    • Liebherr LTM-1400 7.1
  • Services Used

  • By the Numbers

    • 3 Boilers weighing 400,400 lbs
    • Measuring 52’ x 13’ x 26’
Boiler Lift Project
Boiler Lift for Petrochemical
500-ton Liebherr LTM
12-line double-wide Scheuerle SPMTs
Setting Boilers with the Liebherr LTM

Related Projects

Chemical Plant Transport Service

Chemical Plant Expansion Gets Big Lift from Deep South

View Project
Chemical Plant Expansion Gets Big Lift from Deep South

The Deep South team was hard at work at the Geismar Chemical Plant in Louisiana.  Read on to see how our talented crews are using cranes, transporters, and jacking solutions to help construct the largest alpha olefins production facility in the world.

Flare Stack Lift

View Project
Flare Stack Lift

Deep South Crane and Rigging was contracted for a heavy lift project in Norco, Louisiana.  The scope of work required for this lift included lifting two sections of a flare stack and the flare tip.  

Deep South Cranes

400,400 Pound Boiler Lifts

View Project
400,400 Pound Boiler Lifts

Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system and then trans-loaded onto Scheuerle SPMTs in a very congested unit.

A successful job is built on precise planning and safe execution. request a quote