400,400 Pound Boiler Lifts
Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system that was setup outside of the plant. The boilers were lifted and trans-loaded onto 12-line double-wide Scheuerle SPMTs and transported into the Southwest petrochemical refinery through a very congested unit.
Deep South then set them onto their foundations using two 500-ton Liebherr LTM 1400-7.1s and a 265-ton Liebherr LTM 1220-5.1. Each boiler weighed 400,400 pounds and was 52’ long, 13’ wide, and 26’ high.
-
Equipment Used
-
Services Used
-
By the Numbers
- 3 Boilers weighing 400,400 lbs
- Measuring 52’ x 13’ x 26’
Related Projects
Saddle Up: Customized Solutions Place Refinery Column with Care
View Project
Saddle Up: Customized Solutions Place Refinery Column with Care
The Deep South team was tasked to receive, transport and set a 790,025-pound debutanizer. This specialized distillation column measures 174’-3” long with a 21’-3” diameter. The debutanizer was received from an ocean-going vessel at the Port of New Orleans. Once cleared through customs, the debutanizer was loaded on a barge and pushed to a roll-off site 8 hours upriver, and prepared for transport to the refinery.
Combined Gantry/Strand Jack Systems Power Lifts Co-Gen Train
View Project
Combined Gantry/Strand Jack Systems Power Lifts Co-Gen Train
The construction of a combined-cycle power station in Louisiana required a specialty contractor to move, lift and set a STG generator (692,250 lbs.) and HIP turbine (392,420 lbs.).
Flare Stack Lift
View Project
Flare Stack Lift
Deep South Crane and Rigging was contracted for a heavy lift project in Norco, Louisiana. The scope of work required for this lift included lifting two sections of a flare stack and the flare tip.