400,400 Pound Boiler Lifts
Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system that was setup outside of the plant. The boilers were lifted and trans-loaded onto 12-line double-wide Scheuerle SPMTs and transported into the Southwest petrochemical refinery through a very congested unit.
Deep South then set them onto their foundations using two 500-ton Liebherr LTM 1400-7.1s and a 265-ton Liebherr LTM 1220-5.1. Each boiler weighed 400,400 pounds and was 52’ long, 13’ wide, and 26’ high.
-
Equipment Used
-
Services Used
-
By the Numbers
- 3 Boilers weighing 400,400 lbs
- Measuring 52’ x 13’ x 26’
Related Projects
Pressed for Time
View Project
Pressed for Time
A vehicle manufacturer’s large stamping press—a massive machine used for shaping body panels—is online and operational thanks to efficient installation by Deep South. The three primary components included a 181-ton press bed (27.72’ L x 16.4’ W x 13.12’ H), 250-ton press crown (28.38’ L x 16.4’ W x 13.12’ H) and a 92-ton press slide (21’ x 10.83’ x 10.5’).
Cantilever Bar Approach Helps Ease Exchangers Into Place
View Project
Cantilever Bar Approach Helps Ease Exchangers Into Place
Deep South used a cantilever beam (also commonly referred to as a cantilever bar), which incorporates a compact counterweight design with customizable rigging attachment points, to move eight 118,000-pound exchangers into position under an existing steel structure at a refinery optimization project in the Southwest.
Caustic & PreFrac Tower Lift
View Project
Caustic & PreFrac Tower Lift
Deep South Crane and Rigging was recently contracted by a southeast petrochemical plant as part of a major pre-turnaround project. In order to de-bottleneck ethylene production, Deep South erected a caustic tower and a prefrac tower.