37 Vessel Heavy Haul
As part of an expansion project in the Southwest, Deep South received, barged, and transported 37 vessels to complete this project. Pictured here is the largest of those vessels, an 800-ton quench tower. Using Deep South’s 1,000-ton rocking bolsters, in-house designed transport saddles, and a 120’ bridge ramp, Deep South was able to negotiate the barge roll off and 4 miles of roadways through town to reach the job site. This included crossing three jumper bridges, the longest measuring 120’ in length.
-
Equipment Used
-
Services Used
-
By the Numbers
- 37 Vessels
- Largest was 800T, 120' Long
Related Projects
Facilitating a Refinery Column Placement in Tight Confines
View Project
Facilitating a Refinery Column Placement in Tight Confines
Transporting, placing, and lifting a refinery column — one that is comparable to the height and weight of the Statue of Liberty — is a familiar challenge for heavy lift, heavy haul experts like Deep South. Maneuvering it around existing racks and systems adds another layer of complexity.
Coal Export Facility System Upgrade
View Project
Coal Export Facility System Upgrade
At a coal export terminal in Southeast Texas, Deep South provided multiple single and tandem lifts to install this conveyor system during a facility upgrade.
A Marathon Job, Literally
View Project
A Marathon Job, Literally
As seen in American Cranes and Transport Magazine
Transforming a 200-acre sugarcane field in Garyville, LA into a state-of-the-art refinery required a $3.8 billion investment and the work of a cadre of contractors with expertise that spanned the entire spectrum of engineering, construction, and rigging. Construction on the Marathon GME project started in March of 2007, and by December of 2009 the refinery was mechanically complete.