Tight Tailswing, Turnkey Solution
In the Southeast, Deep South performed a complex turnkey project that required equipment modification and careful planning.
To begin, Deep South received a reactor from the ship of origin and transported it via barge to a petrochemical facility up river. Using Goldhofer SPMTs, Deep South off-loaded the vessel from the barge and negotiated very tight turns and low pipe racks with minimum clearance to get it to the final off-loading location. Five-hundred-ton gantries were used to off-load to temporary supports.
Deep South modified the 1,500-ton VersaCrane TC-24000 specifically for this project to accommodate a very tight tail swing requirement. The vessel weighed 420,000 pounds, measured 100’ long and was lifted using 200’ of boom at a 95’ radius. Scheuerle SPMTs were used with the tailing frame to tail the load due to space constraints.
-
Equipment Used
-
Services Used
-
By the Numbers
- Vessel Weighed 420,000 Pounds
- Vessel Measured 100’ Long
- VersaCrane was 200’ of Boom at a 95’ Radius
Related Projects
Chemical Plant Expansion Gets Big Lift from Deep South
View Project
Chemical Plant Expansion Gets Big Lift from Deep South
The Deep South team was hard at work at the Geismar Chemical Plant in Louisiana. Read on to see how our talented crews are using cranes, transporters, and jacking solutions to help construct the largest alpha olefins production facility in the world.
Flare Stack Lift
View Project
Flare Stack Lift
Deep South Crane and Rigging was contracted for a heavy lift project in Norco, Louisiana. The scope of work required for this lift included lifting two sections of a flare stack and the flare tip.
200 Lifts at Michigan Power Plant
View Project
200 Lifts at Michigan Power Plant
At a Michigan power plant, Deep South utilized a 660-ton Demag CC-2800 to complete 200 lifts over an 8 month duration.