Tight Tailswing, Turnkey Solution
In the Southeast, Deep South performed a complex turnkey project that required equipment modification and careful planning.
To begin, Deep South received a reactor from the ship of origin and transported it via barge to a petrochemical facility up river. Using Goldhofer SPMTs, Deep South off-loaded the vessel from the barge and negotiated very tight turns and low pipe racks with minimum clearance to get it to the final off-loading location. Five-hundred-ton gantries were used to off-load to temporary supports.
Deep South modified the 1,500-ton VersaCrane TC-24000 specifically for this project to accommodate a very tight tail swing requirement. The vessel weighed 420,000 pounds, measured 100’ long and was lifted using 200’ of boom at a 95’ radius. Scheuerle SPMTs were used with the tailing frame to tail the load due to space constraints.
-
Equipment Used
-
Services Used
-
By the Numbers
- Vessel Weighed 420,000 Pounds
- Vessel Measured 100’ Long
- VersaCrane was 200’ of Boom at a 95’ Radius
Related Projects
Super-Sized Truss No Problem for High Capacity Crane
View Project
Super-Sized Truss No Problem for High Capacity Crane
Deep South lifted and set double-rail bridge truss sections weighing 800,000 pounds each along a railroad line that crosses the Tug Fork River at Hatfield Bottom near Matewan, WV. Our crews engineered and fabricated custom lifting beams suitable for removing the existing truss bridges and lifting the new bridge spans into place and used our 1,760-ton capacity Terex-Demag CC-8800-1 crawler crane.
Bridge Span Move and Lift Set Pace for New Bridge Completion
View Project
Bridge Span Move and Lift Set Pace for New Bridge Completion
In support of a major bridge construction project in the Midwest, Deep South crews helped transport and install four bridge spans from an off-site staging area to the bridge foundation.
15-Month Turnkey Transport and Erection Project at a Western Iowa Plant
View Project
15-Month Turnkey Transport and Erection Project at a Western Iowa Plant
Deep South was contracted to provide turnkey transportation and field erection services as part of a grassroots fertilizer project at a plant in Western Iowa. Over this 15-month period more than 150 pieces of plant equipment were successfully transported and erected.