As featured in American Cranes & Transport. Click to view a pdf of the article.
Custom Solutions for a 3-Million-Pound Challenge
Two massive reactors, each weighing nearly
three million pounds and standing 143 feet 6 inches tall, journeyed from the
Port of New Orleans up the Mississippi River to a refinery in the Southeast.
From transportation to final placement, the project required customized
solutions at every step to address the unique challenges of the route, site and
massive loads.
Multiple roll-off scenarios were developed to
account for the Mississippi River's ever-changing water levels, with surveying
teams conducting precise field measurements to ensure perfect alignment
throughout the transport corridor. To ensure the transport could adapt to
fluctuating river levels and meet strict Army Corps of Engineers
specifications, Deep South engineered and constructed a specialized heavy-haul
bridge from scratch to carry the reactors over the Mississippi River levee and
its adjacent road.
Riverbank lift
From ship-to-barge transloading at the port to
precise roll-off operations and railroad crossings due to stringent railroad
requirements, every phase demanded meticulous planning and real-time
problem-solving. Deep South used 28 axle lines of triple-wide Scheuerle SPMTs
for roll-off and 28 axle lines of double-wide Scheuerle SPMTs for in-plant
transport.
But delivering these colossal reactors to the
refinery was only the beginning. A second challenging phase lay ahead: lifting
each 3-million-pound reactor into its final position.
Following the Deep South-facilitated reactor
transport, the team was tasked with lifting the two reactors into position,
each weighing nearly 3 million pounds and measuring 143 feet 6 inches long by
21 feet 6 inches wide. The operation required Deep South's 2,500-ton VersaCrane
TC-36000. It was rigged in a customized Configuration 6. This was Deep South's
heaviest field lift in company history.
The lift presented its own set of site-specific
challenges, including a confined space that required a new approach to tailing
the reactors. To support the massive lift and eliminate the need for a tall
crane, the team used a newly designed and fabricated 1,000-ton tailing frame
mounted on a 12-axle-line, quadruple-wide Scheuerle SPMT trailer.
Deep South's team also custom-engineered and
fabricated a 2,000-ton hydraulic pin puller for safe, hands-free rigging
attachment and detachment, which eliminated the need for an additional assist
crane with a man basket. Deep South's custom steel mats and bridge ramps helped
to achieve optimal load distribution for Configuration 6, with 1.2 million
pounds of main counterweight and 2.8 million pounds of hinge counterweight.
Master planning
After nearly three years of extensive planning
and one year of construction and execution, the job was completed safely and on
time thanks to strong teamwork and careful coordination with the client,
according to Deep South President Jeremy Landry.
"From the custom-built heavy-haul bridge
to the customized crane configuration, newly engineered tailing system and
hands-free pin puller, the project required a tailored solution at every
stage," Landry said.
-
Equipment Used
-
Services Used