Southeast Petrochemical Turnaround
Supplying all cranes in two units during a petrochemical turnaround in the Southeast, Deep South supported the change out of old components and reinstallation of new components with 19 cranes working throughout the project. Among the cranes used were the 1800-ton VersaCrane TC-28000, 1,320-ton Terex AC-1000, and the 800-ton Demag AC-700.
Pictured here is the Depropanizer, weighing approximately 410,000 pounds and measuring 90’ long by 17.5’ in diameter, and the Acid Relief Neutralizer, weighing approximately 137,000 pounds and measuring 51’ long by 20’ in diameter. The 1800-ton VersaCrane was setup with 393’ of main boom at a 243’ radius. Cometto trailers were used to transport crane components during assembly and disassembly as well as hauling the two vessels pictured here.
-
Equipment Used
-
Services Used
-
By the Numbers
- 19 Cranes Total
- Largest Vessel Weighed 410,000 lbs and Measured 90’ x 17.5’ in Diameter
- 1800T VersaCrane TC-28000 with 393’ of main boom at a 243’ radius
Related Projects
A Flare for Efficiency
View Project
A Flare for Efficiency
Routine maintenance plant turnarounds are typically anything but straightforward—as a turnaround in the Southeast quickly demonstrated. The effort called for the removal and replacement of three exchangers, as well as a flare modular replacement. The size and location of the exchangers, the tight window for replacement of the flare, and localized high working-wind speeds were a few of the top challenges that the Deep South team were tasked to overcome.
New Orleans Coffee Plant
View Project
New Orleans Coffee Plant
Deep South was contracted to lift and set the top 3 decks of a tugboat wheel house.
15-Month Turnkey Transport and Erection Project at a Western Iowa Plant
View Project
15-Month Turnkey Transport and Erection Project at a Western Iowa Plant
Deep South was contracted to provide turnkey transportation and field erection services as part of a grassroots fertilizer project at a plant in Western Iowa. Over this 15-month period more than 150 pieces of plant equipment were successfully transported and erected.