15-Month Turnkey Transport and Erection Project at a Western Iowa Plant
Deep South Crane and Rigging was contracted to provide turnkey transportation and field erection services as part of a grassroots fertilizer project at a plant in Western Iowa.
Using Goldhofer E-Series and Scheuerle SPMT hydraulic transporters, Deep South offloaded over 80 pieces of equipment from barges. These pieces were transported and staged as a part of the overall project.
Deep South’s 1,000-ton VersaCrane CC-12000 was utilized as the primary lift crane for this project. It was supported by the 660-ton Liebherr LR1600/2. One of the larger lifts featured the transport and erection of a 164’ tall x 17’ diameter absorber vessel. The total weight of this lift was 522 tons. Another on-site transport and erection featured a 158’ tall x 20’ diameter flash vessel that weighed 460 tons.
Over this 15-month period more than 150 pieces of plant equipment were successfully transported and erected.
-
Equipment Used
-
Services Used
-
By the Numbers
Related Projects
Tight Tailswing, Turnkey Solution
View Project
Tight Tailswing, Turnkey Solution
In the Southeast, Deep South performed a complex turnkey project that required equipment modification and careful planning.
400,400 Pound Boiler Lifts
View Project
400,400 Pound Boiler Lifts
Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system and then trans-loaded onto Scheuerle SPMTs in a very congested unit.
A High-pressure Exchange
View Project
A High-pressure Exchange
Assembling the 1,500T VersaCrane™ TC-24000 off site and moving it via SPMT saved this client 15 days of downtime and allowed the refinery unit to run at full capacity until unit shutdown. During the scheduled outage, Deep South was tasked to replace two coke drums, each weighed 452,800 lbs and were 19’-2” outside diameter and 96’-0” long and were comparable in size and weight to the old drums.