15-Month Turnkey Transport and Erection Project at a Western Iowa Plant

Deep South Crane and Rigging was contracted to provide turnkey transportation and field erection services as part of a grassroots fertilizer project at a plant in Western Iowa. 

Using Goldhofer E-Series and Scheuerle SPMT hydraulic transporters, Deep South offloaded over 80 pieces of equipment from barges.  These pieces were transported and staged as a part of the overall project.

Deep South’s 1,000-ton VersaCrane CC-12000 was utilized as the primary lift crane for this project.  It was supported by the 660-ton Liebherr LR1600/2.  One of the larger lifts featured the transport and erection of a 164’ tall x 17’ diameter absorber vessel.  The total weight of this lift was 522 tons.  Another on-site transport and erection featured a 158’ tall x 20’ diameter flash vessel that weighed 460 tons.

Over this 15-month period more than 150 pieces of plant equipment were successfully transported and erected.  

refinery field erection services
Specialty Heavy Transport
heavy lift crane services
Heavy Industrial Crane Services
Heavy Transport Services
Heavy Industrial SPMT Services
Heavy SPMT Transport
SPMT and bridging services
Industrial Heavy Transport Services
refinery field erection services
refinery lifting services
barging transport
barging heavy haul services
heavy haul spmt
heavy haul turnkey services
heavy haul spmt turnkey services
refinery spmt services
heavy transport barging services

Related Projects

Tight Tailswing, Turnkey Solution

View Project
Tight Tailswing, Turnkey Solution

In the Southeast, Deep South performed a complex turnkey project that required equipment modification and careful planning.

Deep South Cranes

400,400 Pound Boiler Lifts

View Project
400,400 Pound Boiler Lifts

Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system and then trans-loaded onto Scheuerle SPMTs in a very congested unit.

heavy lift system

Combined Gantry/Strand Jack Systems Power Lifts Co-Gen Train

View Project
Combined Gantry/Strand Jack Systems Power Lifts Co-Gen Train

The construction of a combined-cycle power station in Louisiana required a specialty contractor to move, lift and set a STG generator (692,250 lbs.) and HIP turbine (392,420 lbs.). 

A successful job is built on precise planning and safe execution. request a quote