Coker Derrick Structure Installation
Deep South hoisted and set the four sections of the coker derrick structure, the heaviest of which weighed 256 tons, and two 450-ton coke drums at a Midwest Refinery using our 2,500-ton VersaCrane TC-36000 and our 275-ton Demag CC-1400. Deep South made the first six lifts with 450’ of main boom in the 2,500-ton VersaCrane and then, due to the final elevation of the derrick, installed an additional 80’ of fixed jib to set the final section of the derrick structure. Deep South also provided all of the rigging systems required to complete this job.
-
Equipment Used
-
Services Used
-
By the Numbers
- 4 Sections of Coker Derrick, Heaviest 256T
- 2 Coke Drums at 450T
Related Projects
Super-Sized Truss No Problem for High Capacity Crane
View Project
Super-Sized Truss No Problem for High Capacity Crane
Deep South lifted and set double-rail bridge truss sections weighing 800,000 pounds each along a railroad line that crosses the Tug Fork River at Hatfield Bottom near Matewan, WV. Our crews engineered and fabricated custom lifting beams suitable for removing the existing truss bridges and lifting the new bridge spans into place and used our 1,760-ton capacity Terex-Demag CC-8800-1 crawler crane.
Turnkey Demolition Facilitates Clean Refinery Modernization
View Project
Turnkey Demolition Facilitates Clean Refinery Modernization
In South America, Deep South demolished and removed three units within a petrochemical facility that was more than 50 years old.
400,400 Pound Boiler Lifts
View Project
400,400 Pound Boiler Lifts
Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system and then trans-loaded onto Scheuerle SPMTs in a very congested unit.