Coker Derrick Structure Installation
Deep South hoisted and set the four sections of the coker derrick structure, the heaviest of which weighed 256 tons, and two 450-ton coke drums at a Midwest Refinery using our 2,500-ton VersaCrane TC-36000 and our 275-ton Demag CC-1400. Deep South made the first six lifts with 450’ of main boom in the 2,500-ton VersaCrane and then, due to the final elevation of the derrick, installed an additional 80’ of fixed jib to set the final section of the derrick structure. Deep South also provided all of the rigging systems required to complete this job.
-
Equipment Used
-
Services Used
-
By the Numbers
- 4 Sections of Coker Derrick, Heaviest 256T
- 2 Coke Drums at 450T
Related Projects
Expert Execution on a Time-Critical LNG Changeout
View Project
Expert Execution on a Time-Critical LNG Changeout
When a critical motor failed at an LNG plant, the clock started immediately. At 680,000 lbs, the motor had never been changed out before.
Beating the Turnaround Clock
View Project
Beating the Turnaround Clock
In the Southwest, a recent turnaround project presented a difficult set of challenges. Crews needed to replace several large pieces of equipment
A Technical Towering Roll, Move, and Lift
View Project
A Technical Towering Roll, Move, and Lift
As part of a complex project for a refinery, the Deep South team was tasked with receiving, transporting and lifting a 114’-7” x 33’-5” x 39’-10” vacuum tower weighing in excess of one million pounds. This multi-step project required considerable planning, technology and creative thinking.