Dismantling and Relocating A Petrochemical Facility

This project included two separate scopes of work. Deep South was originally contracted to dismantle and relocate 9 vessels from a petrochemical plant. The vessels were barged, rolled off, and staged at their new location.

Deep South returned a year later to transport and set the vessels at their final location in the Southwest. The vessels ranged in weight from 82,000 pounds to 1,100,000 pounds. Using 36 lines of Scheuerle SPMTs, the vessels were transported to the crane hook for lifting into final position.

Pictured here is the largest vessel weighing 1,100,000 pounds, being lifted by the 1,800-ton VersaCrane TC-28000 and the 440-ton Terex-Demag CC-2400-1 as the tail crane.

Deep South Employees
Deep South Crane Heavy Equipment
Deep South Crane Heavy Haul

Related Projects

Heavy lift tail crane

Tailing Over a Live Pipe Rack Emphasizes Complex Project

View Project
Tailing Over a Live Pipe Rack Emphasizes Complex Project

From a tricky bridge crossing to a complex coordinated lift, Deep South facilitated the delivery and setting of components for a petrochemical facility acid modification and upgrade project in Louisiana. The key components included a 627,000-pound acid settler, 689,000-pound first stage reactor, acid storage drums and associated parts.

SPMT Project Deep South

Blue Sea Modular Transport

View Project
Blue Sea Modular Transport

In South Carolina, Deep South was contracted to transport and secure seven modules from the fabricator shop to a barge site via Scheuerle SPMTs.

Vessel Heavy Haul

37 Vessel Heavy Haul

View Project
37 Vessel Heavy Haul

As part of an expansion project in the Southwest, Deep South received, barged, and transported 37 vessels to complete this project.

A successful job is built on precise planning and safe execution. request a quote