Dismantling and Relocating A Petrochemical Facility
This project included two separate scopes of work. Deep South was originally contracted to dismantle and relocate 9 vessels from a petrochemical plant. The vessels were barged, rolled off, and staged at their new location.
Deep South returned a year later to transport and set the vessels at their final location in the Southwest. The vessels ranged in weight from 82,000 pounds to 1,100,000 pounds. Using 36 lines of Scheuerle SPMTs, the vessels were transported to the crane hook for lifting into final position.
Pictured here is the largest vessel weighing 1,100,000 pounds, being lifted by the 1,800-ton VersaCrane TC-28000 and the 440-ton Terex-Demag CC-2400-1 as the tail crane.
-
Equipment Used
-
Services Used
-
By the Numbers
- Vessel Weights: 82,000 pounds - 1,100,000 lbs
Related Projects
Precision Lifts in Tight Quarters
View Project
Precision Lifts in Tight Quarters
Deep South was tasked to move, lift, and set several large components as part of a larger, multi-phase project for a refinery customer in the Southwest.
Many Lifts, One Solution: Modular Lift System Flexes Hydraulic Muscles During Process Plant Overhaul
View Project
Many Lifts, One Solution: Modular Lift System Flexes Hydraulic Muscles During Process Plant Overhaul
Deep South crews were challenged to haul, lift, and set 84 modules, including three towers (one measuring 100’ long, 350,000 lbs.) as well as various pieces of process equipment, such as piping, tanks, PDC buildings, and transformers—all within a tight schedule. Many of the modules had offset centers of gravity further complicating the lift and set.
Turnkey Demolition Facilitates Clean Refinery Modernization
View Project
Turnkey Demolition Facilitates Clean Refinery Modernization
In South America, Deep South demolished and removed three units within a petrochemical facility that was more than 50 years old.