Dismantling and Relocating A Petrochemical Facility
This project included two separate scopes of work. Deep South was originally contracted to dismantle and relocate 9 vessels from a petrochemical plant. The vessels were barged, rolled off, and staged at their new location.
Deep South returned a year later to transport and set the vessels at their final location in the Southwest. The vessels ranged in weight from 82,000 pounds to 1,100,000 pounds. Using 36 lines of Scheuerle SPMTs, the vessels were transported to the crane hook for lifting into final position.
Pictured here is the largest vessel weighing 1,100,000 pounds, being lifted by the 1,800-ton VersaCrane TC-28000 and the 440-ton Terex-Demag CC-2400-1 as the tail crane.
-
Equipment Used
-
Services Used
-
By the Numbers
- Vessel Weights: 82,000 pounds - 1,100,000 lbs
Related Projects
Bridge Limits: Deep South Facilitates Complex Multi-Stages Delivery of Million Pound Converter
View Project
Bridge Limits: Deep South Facilitates Complex Multi-Stages Delivery of Million Pound Converter
In preparation for a capacity expansion project, Deep South transported a 939,327-pound ammonia converter shell from the manufacturer to its plant in Donaldsonville, La. The trek required moving the system about 135 miles by water to a barge unloading site and 30 miles over the road.
Scheuerles Haul 750 Ton Tugboat
View Project
Scheuerles Haul 750 Ton Tugboat
Deep South was contracted to transport a 750-ton tugboat.
Southeast Petrochemical Turnaround
View Project
Southeast Petrochemical Turnaround
Supplying all cranes in two units during a petrochemical turnaround in the Southeast, Deep South supported the change out of old components and reinstallation of new components with 19 cranes working throughout the project.