Dismantling and Relocating A Petrochemical Facility
This project included two separate scopes of work. Deep South was originally contracted to dismantle and relocate 9 vessels from a petrochemical plant. The vessels were barged, rolled off, and staged at their new location.
Deep South returned a year later to transport and set the vessels at their final location in the Southwest. The vessels ranged in weight from 82,000 pounds to 1,100,000 pounds. Using 36 lines of Scheuerle SPMTs, the vessels were transported to the crane hook for lifting into final position.
Pictured here is the largest vessel weighing 1,100,000 pounds, being lifted by the 1,800-ton VersaCrane TC-28000 and the 440-ton Terex-Demag CC-2400-1 as the tail crane.
-
Equipment Used
-
Services Used
-
By the Numbers
- Vessel Weights: 82,000 pounds - 1,100,000 lbs
Related Projects
A High-pressure Exchange
View Project
A High-pressure Exchange
Assembling the 1,500T VersaCrane™ TC-24000 off site and moving it via SPMT saved this client 15 days of downtime and allowed the refinery unit to run at full capacity until unit shutdown. During the scheduled outage, Deep South was tasked to replace two coke drums, each weighed 452,800 lbs and were 19’-2” outside diameter and 96’-0” long and were comparable in size and weight to the old drums.
Power Move: Transformer Lift and Staging Rises to the Occasion
View Project
Power Move: Transformer Lift and Staging Rises to the Occasion
In support of a power plant project in the Northeast, Deep South crews were tasked with transporting and staging four transformers, each 22’ high, 12’ wide and 14’ long and weighing 314,000 pounds.
Dismantling and Relocating A Petrochemical Facility
View Project
Dismantling and Relocating A Petrochemical Facility
Deep South was contracted to dismantle and relocate 9 vessels from a petrochemical plant using a combination of barging, heavy transport, and heavy lift services.