A High Lift for Health
As part of an HVAC system upgrade, a client needed to place a new industrial-size, 25,000-pound chiller onto the roof of its multi-story medical facility in New Orleans, LA. The challenges on this project, located in a congested urban environment, ranged from limited space to set up cranes and associated support equipment to a requirement that trees along the roadway could not to be disturbed. Also, the road and medical facility had to remain open throughout the effort.
The Setup
To stabilize the ground, the Deep South crew first set outrigger mats that extended over and above street curbs to stabilize the ground.
Once the site was prepared, a 550-ton Liebherr LTM-1450 crane with luffing jib was delivered from Baton Rouge to the site. Crews assembled the crane with support from an assist crane over the course of 10 hours. Notably, the assist crane had to be located on a nearby cross street because of the limited roadway space.
Once assembled, crews performed several lifts with the necessary structural iron framing that would hold the HVAC system.
The Lift
The day after the crane was assembled, crews lifted and set the chiller, along with miscellaneous piping, into position on the roof for installation over a course of four hours. On the third day, the crane was disassembled and returned to Baton Rouge.
The assembly and disassembly of the crane as well as the lift of the chiller and miscellaneous equipment were completed with precision and safety—all while keeping the roads and the medical facility open and avoiding nearby obstructions.
Related Projects
Full Steam Ahead with New Boiler Transport
View Project
Full Steam Ahead with New Boiler Transport
The transport of a 350,000-pound “therm” steam boiler from fabricator to plant, a distance of 375 miles, required creativity and experience to safely move the component, despite some clearance limitations and unexpected construction along the way.
A Technical Towering Roll, Move, and Lift
View Project
A Technical Towering Roll, Move, and Lift
As part of a complex project for a refinery, the Deep South team was tasked with receiving, transporting and lifting a 114’-7” x 33’-5” x 39’-10” vacuum tower weighing in excess of one million pounds. This multi-step project required considerable planning, technology and creative thinking.
Extreme Circumstances Call for Extreme Measures: A Narrow Canal Requires a Side Roll-Off
View Project
Extreme Circumstances Call for Extreme Measures: A Narrow Canal Requires a Side Roll-Off
Deep South was contracted to deliver a 750,000-pound reactor to a refinery in northern Illinois. The navigable waterway, a highly-trafficked 125-foot wide canal, required a side roll-off.