A High Lift for Health
As part of an HVAC system upgrade, a client needed to place a new industrial-size, 25,000-pound chiller onto the roof of its multi-story medical facility in New Orleans, LA. The challenges on this project, located in a congested urban environment, ranged from limited space to set up cranes and associated support equipment to a requirement that trees along the roadway could not to be disturbed. Also, the road and medical facility had to remain open throughout the effort.
The Setup
To stabilize the ground, the Deep South crew first set outrigger mats that extended over and above street curbs to stabilize the ground.
Once the site was prepared, a 550-ton Liebherr LTM-1450 crane with luffing jib was delivered from Baton Rouge to the site. Crews assembled the crane with support from an assist crane over the course of 10 hours. Notably, the assist crane had to be located on a nearby cross street because of the limited roadway space.
Once assembled, crews performed several lifts with the necessary structural iron framing that would hold the HVAC system.
The Lift
The day after the crane was assembled, crews lifted and set the chiller, along with miscellaneous piping, into position on the roof for installation over a course of four hours. On the third day, the crane was disassembled and returned to Baton Rouge.
The assembly and disassembly of the crane as well as the lift of the chiller and miscellaneous equipment were completed with precision and safety—all while keeping the roads and the medical facility open and avoiding nearby obstructions.
Related Projects
Creative Thinking Keeps Transport Costs Low and Delivery Quick
View Project
Creative Thinking Keeps Transport Costs Low and Delivery Quick
As part of a natural gas fractionation project, an EPC contractor needed to transport two large drums to the customer’s facility.
Overcoming Poor Weather Conditions in Michigan to Lift 12 Components
View Project
Overcoming Poor Weather Conditions in Michigan to Lift 12 Components
Deep South set the first of 12 components ranging from 85,000 pounds to 110,000 pounds using the 1,400-ton Demag CC-6800 at a mining facility in Michigan.
A Marathon Job, Literally
View Project
A Marathon Job, Literally
As seen in American Cranes and Transport Magazine
Transforming a 200-acre sugarcane field in Garyville, LA into a state-of-the-art refinery required a $3.8 billion investment and the work of a cadre of contractors with expertise that spanned the entire spectrum of engineering, construction, and rigging. Construction on the Marathon GME project started in March of 2007, and by December of 2009 the refinery was mechanically complete.