A High Lift for Health
As part of an HVAC system upgrade, a client needed to place a new industrial-size, 25,000-pound chiller onto the roof of its multi-story medical facility in New Orleans, LA. The challenges on this project, located in a congested urban environment, ranged from limited space to set up cranes and associated support equipment to a requirement that trees along the roadway could not to be disturbed. Also, the road and medical facility had to remain open throughout the effort.
The Setup
To stabilize the ground, the Deep South crew first set outrigger mats that extended over and above street curbs to stabilize the ground.
Once the site was prepared, a 550-ton Liebherr LTM-1450 crane with luffing jib was delivered from Baton Rouge to the site. Crews assembled the crane with support from an assist crane over the course of 10 hours. Notably, the assist crane had to be located on a nearby cross street because of the limited roadway space.
Once assembled, crews performed several lifts with the necessary structural iron framing that would hold the HVAC system.
The Lift
The day after the crane was assembled, crews lifted and set the chiller, along with miscellaneous piping, into position on the roof for installation over a course of four hours. On the third day, the crane was disassembled and returned to Baton Rouge.
The assembly and disassembly of the crane as well as the lift of the chiller and miscellaneous equipment were completed with precision and safety—all while keeping the roads and the medical facility open and avoiding nearby obstructions.
Related Projects
Complex Refinery Turnaround Delivered with Precision
View Project
Complex Refinery Turnaround Delivered with Precision
A five-week equipment turnaround at a refinery in the Southeast required multiple equipment transports, removals, and replacements across a large work area.
Saddle Up: Customized Solutions Place Refinery Column with Care
View Project
Saddle Up: Customized Solutions Place Refinery Column with Care
The Deep South team was tasked to receive, transport and set a 790,025-pound debutanizer. This specialized distillation column measures 174’-3” long with a 21’-3” diameter. The debutanizer was received from an ocean-going vessel at the Port of New Orleans. Once cleared through customs, the debutanizer was loaded on a barge and pushed to a roll-off site 8 hours upriver, and prepared for transport to the refinery.
Many Lifts, One Solution: Modular Lift System Flexes Hydraulic Muscles During Process Plant Overhaul
View Project
Many Lifts, One Solution: Modular Lift System Flexes Hydraulic Muscles During Process Plant Overhaul
Deep South crews were challenged to haul, lift, and set 84 modules, including three towers (one measuring 100’ long, 350,000 lbs.) as well as various pieces of process equipment, such as piping, tanks, PDC buildings, and transformers—all within a tight schedule. Many of the modules had offset centers of gravity further complicating the lift and set.