400,400 Pound Boiler Lifts
Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system that was setup outside of the plant. The boilers were lifted and trans-loaded onto 12-line double-wide Scheuerle SPMTs and transported into the Southwest petrochemical refinery through a very congested unit.
Deep South then set them onto their foundations using two 500-ton Liebherr LTM 1400-7.1s and a 265-ton Liebherr LTM 1220-5.1. Each boiler weighed 400,400 pounds and was 52’ long, 13’ wide, and 26’ high.
-
Equipment Used
-
Services Used
-
By the Numbers
- 3 Boilers weighing 400,400 lbs
- Measuring 52’ x 13’ x 26’
Related Projects
Scheuerle Highway Trailers Key To Deep South Crane Heavy Haul
View Project
Scheuerle Highway Trailers Key To Deep South Crane Heavy Haul
Deep South Crane & Rigging hauled two manifold skids from Zachary, Louisiana to the Botsco Terminal in Laporte, Texas using Scheuerle highway trailers. This equipment allowed Deep South to expedite permitting to 1 week’s time.
Dismantling and Relocating A Petrochemical Facility
View Project
Dismantling and Relocating A Petrochemical Facility
Deep South was contracted to dismantle and relocate 9 vessels from a petrochemical plant using a combination of barging, heavy transport, and heavy lift services.
Mitigating the Mississippi
View Project
Mitigating the Mississippi
Pulling from its resources and years of experience, Deep South designed and fabricated a barge ramp in 2 weeks time meeting the new CORPS requirements and allowing the project to continue on schedule.