400,400 Pound Boiler Lifts

Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system that was setup outside of the plant. The boilers were lifted and trans-loaded onto 12-line double-wide Scheuerle SPMTs and transported into the Southwest petrochemical refinery through a very congested unit.

Deep South then set them onto their foundations using two 500-ton Liebherr LTM 1400-7.1s and a 265-ton Liebherr LTM 1220-5.1. Each boiler weighed 400,400 pounds and was 52’ long, 13’ wide, and 26’ high.

  • Equipment Used

    • Hydraulic Gantries
    • Scheuerle SPMT
    • Liebherr LTM 1220-5.1/5.2
    • Liebherr LTM-1400-7.1
  • Services Used

  • By the Numbers

    • 3 Boilers weighing 400,400 lbs
    • Measuring 52’ x 13’ x 26’
Boiler Lift Project
Boiler Lift for Petrochemical
500-ton Liebherr LTM
12-line double-wide Scheuerle SPMTs
Setting Boilers with the Liebherr LTM

Related Projects

heavy lift crane services

15-Month Turnkey Transport and Erection Project at a Western Iowa Plant

View Project
15-Month Turnkey Transport and Erection Project at a Western Iowa Plant

Deep South was contracted to provide turnkey transportation and field erection services as part of a grassroots fertilizer project at a plant in Western Iowa. Over this 15-month period more than 150 pieces of plant equipment were successfully transported and erected.

Industrial Airpark Lift

View Project
Industrial Airpark Lift

At an industrial airpark in Louisiana, Deep South set steel roof sections weighing 32,000 pounds and measuring 85' long by 30' wide each.

OTR Trailers and Tight Quarter Cranes Key to Successful Project

View Project
OTR Trailers and Tight Quarter Cranes Key to Successful Project

The upper and lower sections of this vessel, weighing 85T and 102T, were transported from the port to the refinery using dual lane Goldhofers.

A successful job is built on precise planning and safe execution. request a quote