200 Lifts at Michigan Power Plant
At a Michigan power plant, Deep South utilized a 660-ton Demag CC-2800 (pictured here) to complete 200 lifts over an 8 month duration. This included multiple bag-house modules and duct sections, weighing up to 85 tons and measuring up to 85 feet in length. In addition, the 160-ton Tadano GR-1600XL-2 was used in the early phase of the project for erecting steel. Extreme temperatures brought 100 inches of snow during this time.
-
Equipment Used
-
Services Used
-
By the Numbers
- 200 Lifts
- Weighing up to 85 Tons
- Measuring up to 85' in Length
- 100" of Snow
Related Projects
Power Move: Transformer Lift and Staging Rises to the Occasion
View Project
Power Move: Transformer Lift and Staging Rises to the Occasion
In support of a power plant project in the Northeast, Deep South crews were tasked with transporting and staging four transformers, each 22’ high, 12’ wide and 14’ long and weighing 314,000 pounds.
124-line SPMT Chemical Reactor Transport
View Project
124-line SPMT Chemical Reactor Transport
In the Southwest, Deep South received three vessels from a heavy lift ship at the Port of Houston, barged the vessels, and transported them to final staging using a total of 124-axle lines Scheuerle SPMT. The heaviest vessel weighed 1,800,000 pounds and the total gross weight at transport for that vessel was 2,300,000 pounds.
Caustic & PreFrac Tower Lift
View Project
Caustic & PreFrac Tower Lift
Deep South Crane and Rigging was recently contracted by a southeast petrochemical plant as part of a major pre-turnaround project. In order to de-bottleneck ethylene production, Deep South erected a caustic tower and a prefrac tower.