Southeast Petrochemical Turnaround
Supplying all cranes in two units during a petrochemical turnaround in the Southeast, Deep South supported the change out of old components and reinstallation of new components with 19 cranes working throughout the project. Among the cranes used were the 1800-ton VersaCrane TC-28000, 1,320-ton Terex AC-1000, and the 800-ton Demag AC-700.
Pictured here is the Depropanizer, weighing approximately 410,000 pounds and measuring 90’ long by 17.5’ in diameter, and the Acid Relief Neutralizer, weighing approximately 137,000 pounds and measuring 51’ long by 20’ in diameter. The 1800-ton VersaCrane was setup with 393’ of main boom at a 243’ radius. Cometto trailers were used to transport crane components during assembly and disassembly as well as hauling the two vessels pictured here.
-
Equipment Used
-
Services Used
-
By the Numbers
- 19 Cranes Total
- Largest Vessel Weighed 410,000 lbs and Measured 90’ x 17.5’ in Diameter
- 1800T VersaCrane TC-28000 with 393’ of main boom at a 243’ radius
Related Projects
Transporters and Cranes Facilitate Processing Plant Upgrade
View Project
Transporters and Cranes Facilitate Processing Plant Upgrade
The movement and replacement of process plant components are a familiar site in in the Texas Gulf Coast region—though not often to the scale and timeline faced by one EPC contractor. Per the client, the contractor was tasked with the haul and lift of two trains of fractionation tower components (debutanizer, depropanizer, splitter and deethanizer) over the course of nine months.
Power Move: Transformer Lift and Staging Rises to the Occasion
View Project
Power Move: Transformer Lift and Staging Rises to the Occasion
In support of a power plant project in the Northeast, Deep South crews were tasked with transporting and staging four transformers, each 22’ high, 12’ wide and 14’ long and weighing 314,000 pounds.
Blue Sea Modular Transport
View Project
Blue Sea Modular Transport
In South Carolina, Deep South was contracted to transport and secure seven modules from the fabricator shop to a barge site via Scheuerle SPMTs.