Southeast Petrochemical Turnaround
Supplying all cranes in two units during a petrochemical turnaround in the Southeast, Deep South supported the change out of old components and reinstallation of new components with 19 cranes working throughout the project. Among the cranes used were the 1800-ton VersaCrane TC-28000, 1,320-ton Terex AC-1000, and the 800-ton Demag AC-700.
Pictured here is the Depropanizer, weighing approximately 410,000 pounds and measuring 90’ long by 17.5’ in diameter, and the Acid Relief Neutralizer, weighing approximately 137,000 pounds and measuring 51’ long by 20’ in diameter. The 1800-ton VersaCrane was setup with 393’ of main boom at a 243’ radius. Cometto trailers were used to transport crane components during assembly and disassembly as well as hauling the two vessels pictured here.
-
Equipment Used
-
Services Used
-
By the Numbers
- 19 Cranes Total
- Largest Vessel Weighed 410,000 lbs and Measured 90’ x 17.5’ in Diameter
- 1800T VersaCrane TC-28000 with 393’ of main boom at a 243’ radius
Related Projects
Managing the Weight of Expectations with Self-Deploying Bridge System
View Project
Managing the Weight of Expectations with Self-Deploying Bridge System
Transporting a 225,000-pound transformer over a bridge with a 30-ton weight limit would typically require the support of multiple assist cranes. With time and space constraints, a Louisiana-based heavy haul company teamed with Deep South to come up with alternative transport possibilities to manage the weight-limited bridge.
Turnaround Efficiency: Lift, Lower and Slide
View Project
Turnaround Efficiency: Lift, Lower and Slide
A major process unit turnaround (TAR) project for a petrochemical plant in the Southwest required some well-planned logistics, over 1,200 craftworkers (at peak) and a comprehensive fleet of cranes, trucks and customized skid (Jack & Slide) systems.
Turnkey in Tight Quarters: Split Trailers Reduce Height with Inches to Spare
View Project
Turnkey in Tight Quarters: Split Trailers Reduce Height with Inches to Spare
For a refinery in the Southeast, Deep South was contracted to remove and replace a derrick structure and two 491,000-pound vessels, each measuring 99’ long and 24’2” diameter.