Southeast Petrochemical Turnaround
Supplying all cranes in two units during a petrochemical turnaround in the Southeast, Deep South supported the change out of old components and reinstallation of new components with 19 cranes working throughout the project. Among the cranes used were the 1800-ton VersaCrane TC-28000, 1,320-ton Terex AC-1000, and the 800-ton Demag AC-700.
Pictured here is the Depropanizer, weighing approximately 410,000 pounds and measuring 90’ long by 17.5’ in diameter, and the Acid Relief Neutralizer, weighing approximately 137,000 pounds and measuring 51’ long by 20’ in diameter. The 1800-ton VersaCrane was setup with 393’ of main boom at a 243’ radius. Cometto trailers were used to transport crane components during assembly and disassembly as well as hauling the two vessels pictured here.
-
Equipment Used
-
Services Used
-
By the Numbers
- 19 Cranes Total
- Largest Vessel Weighed 410,000 lbs and Measured 90’ x 17.5’ in Diameter
- 1800T VersaCrane TC-28000 with 393’ of main boom at a 243’ radius
Related Projects
Creative Thinking Keeps Transport Costs Low and Delivery Quick
View Project
Creative Thinking Keeps Transport Costs Low and Delivery Quick
As part of a natural gas fractionation project, an EPC contractor needed to transport two large drums to the customer’s facility.
Power Move: Transformer Lift and Staging Rises to the Occasion
View Project
Power Move: Transformer Lift and Staging Rises to the Occasion
In support of a power plant project in the Northeast, Deep South crews were tasked with transporting and staging four transformers, each 22’ high, 12’ wide and 14’ long and weighing 314,000 pounds.
A Marathon Job, Literally
View Project
A Marathon Job, Literally
As seen in American Cranes and Transport Magazine
Transforming a 200-acre sugarcane field in Garyville, LA into a state-of-the-art refinery required a $3.8 billion investment and the work of a cadre of contractors with expertise that spanned the entire spectrum of engineering, construction, and rigging. Construction on the Marathon GME project started in March of 2007, and by December of 2009 the refinery was mechanically complete.