200 Lifts at Michigan Power Plant
At a Michigan power plant, Deep South utilized a 660-ton Demag CC-2800 (pictured here) to complete 200 lifts over an 8 month duration. This included multiple bag-house modules and duct sections, weighing up to 85 tons and measuring up to 85 feet in length. In addition, the 160-ton Tadano GR-1600XL-2 was used in the early phase of the project for erecting steel. Extreme temperatures brought 100 inches of snow during this time.
-
Equipment Used
-
Services Used
-
By the Numbers
- 200 Lifts
- Weighing up to 85 Tons
- Measuring up to 85' in Length
- 100" of Snow
Related Projects
Facilitating a Refinery Column Placement in Tight Confines
View Project
Facilitating a Refinery Column Placement in Tight Confines
Transporting, placing, and lifting a refinery column — one that is comparable to the height and weight of the Statue of Liberty — is a familiar challenge for heavy lift, heavy haul experts like Deep South. Maneuvering it around existing racks and systems adds another layer of complexity.
Super-Sized Truss No Problem for High Capacity Crane
View Project
Super-Sized Truss No Problem for High Capacity Crane
Deep South lifted and set double-rail bridge truss sections weighing 800,000 pounds each along a railroad line that crosses the Tug Fork River at Hatfield Bottom near Matewan, WV. Our crews engineered and fabricated custom lifting beams suitable for removing the existing truss bridges and lifting the new bridge spans into place and used our 1,760-ton capacity Terex-Demag CC-8800-1 crawler crane.
Mitigating the Mississippi
View Project
Mitigating the Mississippi
Pulling from its resources and years of experience, Deep South designed and fabricated a barge ramp in 2 weeks time meeting the new CORPS requirements and allowing the project to continue on schedule.