200 Lifts at Michigan Power Plant
At a Michigan power plant, Deep South utilized a 660-ton Demag CC-2800 (pictured here) to complete 200 lifts over an 8 month duration. This included multiple bag-house modules and duct sections, weighing up to 85 tons and measuring up to 85 feet in length. In addition, the 160-ton Tadano GR-1600XL-2 was used in the early phase of the project for erecting steel. Extreme temperatures brought 100 inches of snow during this time.
-
Equipment Used
-
Services Used
-
By the Numbers
- 200 Lifts
- Weighing up to 85 Tons
- Measuring up to 85' in Length
- 100" of Snow
Related Projects
Bridge Span Move and Lift Set Pace for New Bridge Completion
View Project
Bridge Span Move and Lift Set Pace for New Bridge Completion
In support of a major bridge construction project in the Midwest, Deep South crews helped transport and install four bridge spans from an off-site staging area to the bridge foundation.
Overcoming Obstacles: 800-mile Turnkey Challenge with Notable Jack and Slide
View Project
Overcoming Obstacles: 800-mile Turnkey Challenge with Notable Jack and Slide
Using its nationwide resources, Deep South transported a reactor and third stage separator from Oklahoma to Ohio and then to its final destination in the refinery using a combination of barging, over-the-road transportation, jack and slide operations, and heavy lifting.
A Marathon Job, Literally
View Project
A Marathon Job, Literally
As seen in American Cranes and Transport Magazine
Transforming a 200-acre sugarcane field in Garyville, LA into a state-of-the-art refinery required a $3.8 billion investment and the work of a cadre of contractors with expertise that spanned the entire spectrum of engineering, construction, and rigging. Construction on the Marathon GME project started in March of 2007, and by December of 2009 the refinery was mechanically complete.