Cantilever Bar Approach Helps Ease Exchangers into Place

Deep South was contracted to provide turnkey heavy lift and heavy haul services for a refinery optimization project in the Southwest. During the course of the project, the late delivery of eight (8) exchangers, each weighing 118,000 pounds, caused concern about meeting the schedule.

In the original plans, the exchangers would be installed before the surrounding steel structure that supports other vessels and piping. However, because of the delivery delays, the steel structure was already in place when the exchangers arrived for installation.

Deep South’s Project Engineer Chris Warshaw explained, “We had about 1.5 feet of clearance for the exchangers and the necessary rigging. We could have used a jack-and-slide approach but that would have been more expensive and required more time.”

Instead, the team opted for a more cost and schedule friendly approach using a cantilever bar. They used the 1,320-ton Terex AC-1000 hydraulic truck crane with 109-feet of main boom and 80-ton cantilever bar. Warshaw explains, “With the cantilever bar, which incorporates a compact counterweight design with customizable rigging attachment points, we were able to move each of the exchangers into position under the existing steel structure. The compact design worked very well for the tight clearances around the steel structure.”

The placement of the exchangers was completed in one week with no safety issues.

-------------

In our industry, cantilever bars are also commonly referred to as cantilever beams or cantilever beam systems.

  • Equipment Used

  • Services Used

  • By the Numbers

    • Terex AC-1000 with 109-feet of main boom
    • Cantilever Beam System: 80-ton capacity with compact counterweight design and customizable rigging attachment points for a multitude of applications

Related Projects

Heavy lift tail crane

Tailing Over a Live Pipe Rack Emphasizes Complex Project copy

View Project
Tailing Over a Live Pipe Rack Emphasizes Complex Project copy

From a tricky bridge crossing to a complex coordinated lift, Deep South facilitated the delivery and setting of components for a petrochemical facility acid modification and upgrade project in Louisiana. The key components included a 627,000-pound acid settler, 689,000-pound first stage reactor, acid storage drums and associated parts.

SPMT Project Deep South

Blue Sea Modular Transport

View Project
Blue Sea Modular Transport

In South Carolina, Deep South was contracted to transport and secure seven modules from the fabricator shop to a barge site via Scheuerle SPMTs.

Heavy Lift Services for Mining Facility

Overcoming Poor Weather Conditions in Michigan to Lift 12 Components

View Project
Overcoming Poor Weather Conditions in Michigan to Lift 12 Components

Deep South set the first of 12 components ranging from 85,000 pounds to 110,000 pounds using the 1,400-ton Demag CC-6800 at a mining facility in Michigan.

A successful job is built on precise planning and safe execution. request a quote