Cantilever Bar Approach Helps Ease Exchangers into Place

Deep South was contracted to provide turnkey heavy lift and heavy haul services for a refinery optimization project in the Southwest. During the course of the project, the late delivery of eight (8) exchangers, each weighing 118,000 pounds, caused concern about meeting the schedule.

In the original plans, the exchangers would be installed before the surrounding steel structure that supports other vessels and piping. However, because of the delivery delays, the steel structure was already in place when the exchangers arrived for installation.

Deep South’s Project Engineer Chris Warshaw explained, “We had about 1.5 feet of clearance for the exchangers and the necessary rigging. We could have used a jack-and-slide approach but that would have been more expensive and required more time.”

Instead, the team opted for a more cost and schedule friendly approach using a cantilever bar. They used the 1,320-ton Terex AC-1000 hydraulic truck crane with 109-feet of main boom and 80-ton cantilever bar. Warshaw explains, “With the cantilever bar, which incorporates a compact counterweight design with customizable rigging attachment points, we were able to move each of the exchangers into position under the existing steel structure. The compact design worked very well for the tight clearances around the steel structure.”

The placement of the exchangers was completed in one week with no safety issues.

-------------

In our industry, cantilever bars are also commonly referred to as cantilever beams or cantilever beam systems.

  • Equipment Used

  • Services Used

  • By the Numbers

    • Terex AC-1000 with 109-feet of main boom
    • Cantilever Beam System: 80-ton capacity with compact counterweight design and customizable rigging attachment points for a multitude of applications

A successful job is built on precise planning and safe execution. request a quote