37 Vessel Heavy Haul
As part of an expansion project in the Southwest, Deep South received, barged, and transported 37 vessels to complete this project. Pictured here is the largest of those vessels, an 800-ton quench tower. Using Deep South’s 1,000-ton rocking bolsters, in-house designed transport saddles, and a 120’ bridge ramp, Deep South was able to negotiate the barge roll off and 4 miles of roadways through town to reach the job site. This included crossing three jumper bridges, the longest measuring 120’ in length.
-
Equipment Used
-
Services Used
-
By the Numbers
- 37 Vessels
- Largest was 800T, 120' Long
Related Projects
A High-pressure Exchange
View Project
A High-pressure Exchange
Assembling the 1,500T VersaCrane™ TC-24000 off site and moving it via SPMT saved this client 15 days of downtime and allowed the refinery unit to run at full capacity until unit shutdown. During the scheduled outage, Deep South was tasked to replace two coke drums, each weighed 452,800 lbs and were 19’-2” outside diameter and 96’-0” long and were comparable in size and weight to the old drums.
Power Move: Transformer Lift and Staging Rises to the Occasion
View Project
Power Move: Transformer Lift and Staging Rises to the Occasion
In support of a power plant project in the Northeast, Deep South crews were tasked with transporting and staging four transformers, each 22’ high, 12’ wide and 14’ long and weighing 314,000 pounds.
Combined Gantry/Strand Jack Systems Power Lifts Co-Gen Train
View Project
Combined Gantry/Strand Jack Systems Power Lifts Co-Gen Train
The construction of a combined-cycle power station in Louisiana required a specialty contractor to move, lift and set a STG generator (692,250 lbs.) and HIP turbine (392,420 lbs.).