Tight Tailswing, Turnkey Solution
In the Southeast, Deep South performed a complex turnkey project that required equipment modification and careful planning.
To begin, Deep South received a reactor from the ship of origin and transported it via barge to a petrochemical facility up river. Using Goldhofer SPMTs, Deep South off-loaded the vessel from the barge and negotiated very tight turns and low pipe racks with minimum clearance to get it to the final off-loading location. Five-hundred-ton gantries were used to off-load to temporary supports.
Deep South modified the 1,500-ton VersaCrane TC-24000 specifically for this project to accommodate a very tight tail swing requirement. The vessel weighed 420,000 pounds, measured 100’ long and was lifted using 200’ of boom at a 95’ radius. Scheuerle SPMTs were used with the tailing frame to tail the load due to space constraints.
-
Equipment Used
-
Services Used
-
By the Numbers
- Vessel Weighed 420,000 Pounds
- Vessel Measured 100’ Long
- VersaCrane was 200’ of Boom at a 95’ Radius
Related Projects
Haul & Lift of Refinery Combination Tower Goes Off Without a Hitch
View Project
Haul & Lift of Refinery Combination Tower Goes Off Without a Hitch
Load, haul, roll and set — seemingly simple words unless associated with a 555,000-pound, 160-foot long, 18-foot wide, over 19-foot tall refinery combination tower.
Turnkey in Tight Quarters: Split Trailers Reduce Height with Inches to Spare
View Project
Turnkey in Tight Quarters: Split Trailers Reduce Height with Inches to Spare
For a refinery in the Southeast, Deep South was contracted to remove and replace a derrick structure and two 491,000-pound vessels, each measuring 99’ long and 24’2” diameter.
A Marathon Job, Literally
View Project
A Marathon Job, Literally
As seen in American Cranes and Transport Magazine
Transforming a 200-acre sugarcane field in Garyville, LA into a state-of-the-art refinery required a $3.8 billion investment and the work of a cadre of contractors with expertise that spanned the entire spectrum of engineering, construction, and rigging. Construction on the Marathon GME project started in March of 2007, and by December of 2009 the refinery was mechanically complete.