Tight Tailswing, Turnkey Solution
In the Southeast, Deep South performed a complex turnkey project that required equipment modification and careful planning.
To begin, Deep South received a reactor from the ship of origin and transported it via barge to a petrochemical facility up river. Using Goldhofer SPMTs, Deep South off-loaded the vessel from the barge and negotiated very tight turns and low pipe racks with minimum clearance to get it to the final off-loading location. Five-hundred-ton gantries were used to off-load to temporary supports.
Deep South modified the 1,500-ton VersaCrane TC-24000 specifically for this project to accommodate a very tight tail swing requirement. The vessel weighed 420,000 pounds, measured 100’ long and was lifted using 200’ of boom at a 95’ radius. Scheuerle SPMTs were used with the tailing frame to tail the load due to space constraints.
-
Equipment Used
-
Services Used
-
By the Numbers
- Vessel Weighed 420,000 Pounds
- Vessel Measured 100’ Long
- VersaCrane was 200’ of Boom at a 95’ Radius
Related Projects
Multi-Module Mission
View Project
Multi-Module Mission
The heavy haul transport of oil and gas refinery components is always a challenge. Transporting 17 modules, all in the span of two weeks, raised the bar. The modules varied greatly in size and weight. Two of the modules exceeded 260,000 lbs., while 11 were more than 16’ high, three were more than 19’ high, and 13 had widths greater than 18’. Initially, the customer had trouble finding a company to move the modules to their site in Texas.
4 Drum Coker Unit
View Project
4 Drum Coker Unit
Deep South was contracted to complete a full replacement of a four-drum coker unit.
Caustic & PreFrac Tower Lift
View Project
Caustic & PreFrac Tower Lift
Deep South Crane and Rigging was recently contracted by a southeast petrochemical plant as part of a major pre-turnaround project. In order to de-bottleneck ethylene production, Deep South erected a caustic tower and a prefrac tower.