Tight Tailswing, Turnkey Solution
In the Southeast, Deep South performed a complex turnkey project that required equipment modification and careful planning.
To begin, Deep South received a reactor from the ship of origin and transported it via barge to a petrochemical facility up river. Using Goldhofer SPMTs, Deep South off-loaded the vessel from the barge and negotiated very tight turns and low pipe racks with minimum clearance to get it to the final off-loading location. Five-hundred-ton gantries were used to off-load to temporary supports.
Deep South modified the 1,500-ton VersaCrane TC-24000 specifically for this project to accommodate a very tight tail swing requirement. The vessel weighed 420,000 pounds, measured 100’ long and was lifted using 200’ of boom at a 95’ radius. Scheuerle SPMTs were used with the tailing frame to tail the load due to space constraints.
-
Equipment Used
-
Services Used
-
By the Numbers
- Vessel Weighed 420,000 Pounds
- Vessel Measured 100’ Long
- VersaCrane was 200’ of Boom at a 95’ Radius
Related Projects
Turnkey in Tight Quarters: Split Trailers Reduce Height with Inches to Spare
View Project
Turnkey in Tight Quarters: Split Trailers Reduce Height with Inches to Spare
For a refinery in the Southeast, Deep South was contracted to remove and replace a derrick structure and two 491,000-pound vessels, each measuring 99’ long and 24’2” diameter.
Coker Derrick Structure Installation
View Project
Coker Derrick Structure Installation
Deep South hoisted and set the four sections of the coker derrick structure, the heaviest of which weighed 256 tons, and two 450-ton coke drums at a Midwest Refinery using our 2,500-ton VersaCrane TC-36000 and our 275-ton Demag CC-1400.
Mitigating the Mississippi
View Project
Mitigating the Mississippi
Pulling from its resources and years of experience, Deep South designed and fabricated a barge ramp in 2 weeks time meeting the new CORPS requirements and allowing the project to continue on schedule.