400,400 Pound Boiler Lifts
Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system that was setup outside of the plant. The boilers were lifted and trans-loaded onto 12-line double-wide Scheuerle SPMTs and transported into the Southwest petrochemical refinery through a very congested unit.
Deep South then set them onto their foundations using two 500-ton Liebherr LTM 1400-7.1s and a 265-ton Liebherr LTM 1220-5.1. Each boiler weighed 400,400 pounds and was 52’ long, 13’ wide, and 26’ high.
-
Equipment Used
-
Services Used
-
By the Numbers
- 3 Boilers weighing 400,400 lbs
- Measuring 52’ x 13’ x 26’
Related Projects
15 Module Lift and Transport
View Project
15 Module Lift and Transport
Deep South was contracted by a Gulf Coast refinery to transport fifteen modules from a fabrication shop in Port Allen, LA to the site in Norco, LA.
Blue Sea Modular Transport
View Project
Blue Sea Modular Transport
In South Carolina, Deep South was contracted to transport and secure seven modules from the fabricator shop to a barge site via Scheuerle SPMTs.
Mitigating the Mississippi
View Project
Mitigating the Mississippi
Pulling from its resources and years of experience, Deep South designed and fabricated a barge ramp in 2 weeks time meeting the new CORPS requirements and allowing the project to continue on schedule.