400,400 Pound Boiler Lifts
Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system that was setup outside of the plant. The boilers were lifted and trans-loaded onto 12-line double-wide Scheuerle SPMTs and transported into the Southwest petrochemical refinery through a very congested unit.
Deep South then set them onto their foundations using two 500-ton Liebherr LTM 1400-7.1s and a 265-ton Liebherr LTM 1220-5.1. Each boiler weighed 400,400 pounds and was 52’ long, 13’ wide, and 26’ high.
-
Equipment Used
-
Services Used
-
By the Numbers
- 3 Boilers weighing 400,400 lbs
- Measuring 52’ x 13’ x 26’
Related Projects
Full Steam Ahead with New Boiler Transport
View Project
Full Steam Ahead with New Boiler Transport
The transport of a 350,000-pound “therm” steam boiler from fabricator to plant, a distance of 375 miles, required creativity and experience to safely move the component, despite some clearance limitations and unexpected construction along the way.
Caustic & PreFrac Tower Lift
View Project
Caustic & PreFrac Tower Lift
Deep South Crane and Rigging was recently contracted by a southeast petrochemical plant as part of a major pre-turnaround project. In order to de-bottleneck ethylene production, Deep South erected a caustic tower and a prefrac tower.
Overcoming Poor Weather Conditions in Michigan to Lift 12 Components
View Project
Overcoming Poor Weather Conditions in Michigan to Lift 12 Components
Deep South set the first of 12 components ranging from 85,000 pounds to 110,000 pounds using the 1,400-ton Demag CC-6800 at a mining facility in Michigan.