Related Projects
Turnaround Efficiency: Lift, Lower and Slide
View Project
Turnaround Efficiency: Lift, Lower and Slide
A major process unit turnaround (TAR) project for a petrochemical plant in the Southwest required some well-planned logistics, over 1,200 craftworkers (at peak) and a comprehensive fleet of cranes, trucks and customized skid (Jack & Slide) systems.
Overcoming Obstacles: 800-mile Turnkey Challenge with Notable Jack and Slide
View Project
Overcoming Obstacles: 800-mile Turnkey Challenge with Notable Jack and Slide
Using its nationwide resources, Deep South transported a reactor and third stage separator from Oklahoma to Ohio and then to its final destination in the refinery using a combination of barging, over-the-road transportation, jack and slide operations, and heavy lifting.
An Ammonia Advantage
View Project
An Ammonia Advantage
With ease and precision, Deep South moved an almost one-million-pound ammonia converter and a 213,848-pound cartridge onto a barge and across a levee.