Southeast Petrochemical Turnaround
Supplying all cranes in two units during a petrochemical turnaround in the Southeast, Deep South supported the change out of old components and reinstallation of new components with 19 cranes working throughout the project. Among the cranes used were the 1800-ton VersaCrane TC-28000, 1,320-ton Terex AC-1000, and the 800-ton Demag AC-700.
Pictured here is the Depropanizer, weighing approximately 410,000 pounds and measuring 90’ long by 17.5’ in diameter, and the Acid Relief Neutralizer, weighing approximately 137,000 pounds and measuring 51’ long by 20’ in diameter. The 1800-ton VersaCrane was setup with 393’ of main boom at a 243’ radius. Cometto trailers were used to transport crane components during assembly and disassembly as well as hauling the two vessels pictured here.
-
Equipment Used
-
Services Used
-
By the Numbers
- 19 Cranes Total
- Largest Vessel Weighed 410,000 lbs and Measured 90’ x 17.5’ in Diameter
- 1800T VersaCrane TC-28000 with 393’ of main boom at a 243’ radius
Related Projects
Super-Sized Truss No Problem for High Capacity Crane
View Project
Super-Sized Truss No Problem for High Capacity Crane
Deep South lifted and set double-rail bridge truss sections weighing 800,000 pounds each along a railroad line that crosses the Tug Fork River at Hatfield Bottom near Matewan, WV. Our crews engineered and fabricated custom lifting beams suitable for removing the existing truss bridges and lifting the new bridge spans into place and used our 1,760-ton capacity Terex-Demag CC-8800-1 crawler crane.
Caustic & PreFrac Tower Lift
View Project
Caustic & PreFrac Tower Lift
Deep South Crane and Rigging was recently contracted by a southeast petrochemical plant as part of a major pre-turnaround project. In order to de-bottleneck ethylene production, Deep South erected a caustic tower and a prefrac tower.
Turnkey Demolition Facilitates Clean Refinery Modernization
View Project
Turnkey Demolition Facilitates Clean Refinery Modernization
In South America, Deep South demolished and removed three units within a petrochemical facility that was more than 50 years old.