Dismantling and Relocating A Petrochemical Facility
This project included two separate scopes of work. Deep South was originally contracted to dismantle and relocate 9 vessels from a petrochemical plant. The vessels were barged, rolled off, and staged at their new location.
Deep South returned a year later to transport and set the vessels at their final location in the Southwest. The vessels ranged in weight from 82,000 pounds to 1,100,000 pounds. Using 36 lines of Scheuerle SPMTs, the vessels were transported to the crane hook for lifting into final position.
Pictured here is the largest vessel weighing 1,100,000 pounds, being lifted by the 1,800-ton VersaCrane TC-28000 and the 440-ton Terex-Demag CC-2400-1 as the tail crane.
-
Equipment Used
-
Services Used
-
By the Numbers
- Vessel Weights: 82,000 pounds - 1,100,000 lbs
Related Projects
Complex Refinery Turnaround Delivered with Precision
View Project
Complex Refinery Turnaround Delivered with Precision
A five-week equipment turnaround at a refinery in the Southeast required multiple equipment transports, removals, and replacements across a large work area.
Full Steam Ahead with New Boiler Transport
View Project
Full Steam Ahead with New Boiler Transport
The transport of a 350,000-pound “therm” steam boiler from fabricator to plant, a distance of 375 miles, required creativity and experience to safely move the component, despite some clearance limitations and unexpected construction along the way.
Lifting the Dome
View Project
Lifting the Dome
Using the 660-ton Demag CC-2800-1, Deep South successfully set this 244’ in diameter geodesic dome weighing approximately 145,000 pounds.