Dismantling and Relocating A Petrochemical Facility
This project included two separate scopes of work. Deep South was originally contracted to dismantle and relocate 9 vessels from a petrochemical plant. The vessels were barged, rolled off, and staged at their new location.
Deep South returned a year later to transport and set the vessels at their final location in the Southwest. The vessels ranged in weight from 82,000 pounds to 1,100,000 pounds. Using 36 lines of Scheuerle SPMTs, the vessels were transported to the crane hook for lifting into final position.
Pictured here is the largest vessel weighing 1,100,000 pounds, being lifted by the 1,800-ton VersaCrane TC-28000 and the 440-ton Terex-Demag CC-2400-1 as the tail crane.
-
Equipment Used
-
Services Used
-
By the Numbers
- Vessel Weights: 82,000 pounds - 1,100,000 lbs
Related Projects
Dismantling and Relocating A Petrochemical Facility
View Project
Dismantling and Relocating A Petrochemical Facility
Deep South was contracted to dismantle and relocate 9 vessels from a petrochemical plant using a combination of barging, heavy transport, and heavy lift services.
Overcoming Limited Space with Specialty Tools
View Project
Overcoming Limited Space with Specialty Tools
In the Midwest, Deep South transported and set a tower weighing 227,000 pounds and measuring 134’ long by 8’-2" in diameter.
A Marathon Job, Literally
View Project
A Marathon Job, Literally
As seen in American Cranes and Transport Magazine
Transforming a 200-acre sugarcane field in Garyville, LA into a state-of-the-art refinery required a $3.8 billion investment and the work of a cadre of contractors with expertise that spanned the entire spectrum of engineering, construction, and rigging. Construction on the Marathon GME project started in March of 2007, and by December of 2009 the refinery was mechanically complete.