Custom Connections Deliver Heavy Systems Safely, Timely, Cost Effectively
The critical elements of any petrochemical operation include heavy and large components that range from cold boxes, pipe rack modules and reactors. Moving these systems from fabricator to plant and setting in place, particularly into tight spaces, requires considerable logistical planning and specialized equipment.
Deep South has put its transport and skills to work for a heavy industrial project in the Southwest that required Deep South to direct discharge from ships gear to barge, haul and sett a cold box, depropanizer and six modules.
Transport Techniques
One of the challenging transport components was moving the 448,000-pound cold box from New Iberia, LA to Baytown, TX.
Measuring 84β x 24β x 25β, Deep South crews moved this massive cold box from the fabricatorβs facility to a nearby port using a double-wide, 16-axle-line Scheuerle SPMT, staging cans and mats for barge shipment. Crews met the barge in Cedar Bayou, TX and loaded it onto another double-wide, 16-axle-line Scheuerle SPMT.
The cold box was then prepped for over-the-road transport using an 18-foot-wide, 12-line Dual Lane Goldhofer. Deep Southβs specialized Dual Lane allowed crossing over Interstate-10 via an overpass, which saved the customer money and time[ML1] . Obstructions along surface roads required in-depth coordination with the Texas DOT, rail authorities and utilities in order to remove/reset communication wires, utility poles, railroad arms and streetlights.
Once onsite, Deep South used an 1,800-ton VersaCrane TC-28000 (main 400 kips/aux 960 kips) with a 500-ton Liebherr LTM 1400-7.1 tail crane.
The 492,500-pound depropanizer required similar logistics preparation. This 212β x 15β diameter vessel was loaded at the fabrication shop in Cypress, TX using a 500-ton gantry onto two 8-axle-line Dual Lane Goldhofer in a bolster configuration along with two prime movers. The depropanizer was transported 300 miles over the road to the clientβs plant. The transport of the depropanizer was estimated to take four days; Deep South made the move in three.
Modular Move
Along with the depropanizer and cold box, Deep South was tasked to move six modules:
- Module A (110β x 32β x 38β) - 498,690 pounds
- Module B (81β x 32β x 38β) - 436,850 pounds
- Module C (45β x 32β x 38β) - 225,000 pounds
- Module D (75β x 32β x 38β) - 348,000 pounds
- Module E (116β x 32β x 38β) - 512,900 pounds
- Module F (45β x 32β x 38β) - 224,986 pounds
The modules were built in Korea and were shipped to the port of Houston, TX. Deep South received the cargo direct discharge to three separate barges and engineered, secured and coordinated with the port and barging company for flawless operation.
Once the barge arrived at Cedar Bayou, Deep South crews used a 24-line double-wide Scheuerle SPMT and a 30-axle-line double-wide Scheuerle SPMT to move four of the modules, and another 30 axle-line double-wide SPMT to transport the modules to the plant 8.5 miles away to a staging area in Mont Belvieu, TX.
By the Numbers
- Barge, haul and set a cold box, depropanizer and six modules
- Depropanizer (212β x 15β) - 492,500 pounds
- Cold box (84β x 24β x 25β) - 448,000 pounds
- Largest module (110β x 32β x 38β) - 498,690 pounds
The entire transport was planned and orchestrated by Deep South with all public and private entities including the Texas DOT. With help from a dozen Harris County police officers as well as a third party to manage barricades, crews began moving the modules at 10pm at night along local roads and state highways. The entire moved required 12 bucket trucks provided by a third-party contractor and four Comcast trucks to remove and reset traffic lights, communication wires and utilities.
Crews moved two modules per weekend with a total time of 13 hours per module. At the staging area, crews had already prepared the designated laydown yard with laminated mats and the 1,500-ton VersaCrane TC-24000 in Configuration 6.
Of note, these are the largest modules ever transported to Mont Belvieu.
Framed & Set
Along with the TC-24000, crews needed to find way to lift the modules without tail rigging, which would have interfered with the existing platforms.
Deep South designed and fabricated a specialized tailing frame to eliminate the use of tail rigging. The base was made large enough to bolt onto the base of the modules. Great communication between the transport crew and our operators of TC-24000 allowed this tailing process to work flawlessly.
Deep South then used the TC-24000 crane to lift each module using the custom bases until they were upright. Great communication between the transport crew and our operators of TC-24000 allowed this tailing process to work flawlessly.
Deep South lifted six modules in 8 days.