Related Projects
Combined Gantry/Strand Jack Systems Power Lifts Co-Gen Train
View Project
Combined Gantry/Strand Jack Systems Power Lifts Co-Gen Train
The construction of a combined-cycle power station in Louisiana required a specialty contractor to move, lift and set a STG generator (692,250 lbs.) and HIP turbine (392,420 lbs.).
Precision Meets Power
View Project
Precision Meets Power
Replacing a 650-kip reactor head in the Southwest required Deep South’s team to fit a crane into a tight space where others had been unable to do so. The job involved precise execution to build a high-capacity crane over a pipe rack and into a confined space, which called for the assistance of our 800-ton gantry system, 500-ton Liebherr LTM 1400-7.1, and 265-ton Liebherr LTM 1220-5.1.
An Ammonia Advantage
View Project
An Ammonia Advantage
With ease and precision, Deep South moved an almost one-million-pound ammonia converter and a 213,848-pound cartridge onto a barge and across a levee.