PROJECTS

Throughout our nearly five decades of experience in heavy lift and transport solutions, we have learned that a successful job is built on precise planning and safe execution. This mindset has allowed our business to grow and positively impact some of the most complex projects across two continents. Take a look at what we can do.

A High-pressure Exchange

View Project
A High-pressure Exchange

Assembling the 1,500T VersaCrane™ TC-24000 off site and moving it via SPMT saved this client 15 days of downtime and allowed the refinery unit to run at full capacity until unit shutdown. During the scheduled outage, Deep South was tasked to replace two coke drums, each weighed 452,800 lbs and were 19’-2” outside diameter and 96’-0” long and were comparable in size and weight to the old drums.

Fast Response to a Custom Turnaround

View Project
Fast Response to a Custom Turnaround

When an essential industrial unit targeted for replacement began to fail earlier than expected, a plant operator called on Deep South to help transport and replace key components to support an emergency turnaround.

An Award Winning Multi-Scope Lift and Set

View Project
An Award Winning Multi-Scope Lift and Set

As part of a petrochemical facility expansion in Texas, the client needed more than 60 pieces of equipment of various weights and sizes moved and placed in tight confines—in just four months. With very little room for errors or delays, and no time to spare, Deep South’s skilled engineers and managers put together an impressive engineering plan to facilitate a safe and efficient effort.

Facilitating a Refinery Column Placement in Tight Confines

View Project
Facilitating a Refinery Column Placement in Tight Confines

Transporting, placing, and lifting a refinery column — one that is comparable to the height and weight of the Statue of Liberty — is a familiar challenge for heavy lift, heavy haul experts like Deep South. Maneuvering it around existing racks and systems adds another layer of complexity.

Haul & Lift of Refinery Combination Tower Goes Off Without a Hitch

View Project
Haul & Lift of Refinery Combination Tower Goes Off Without a Hitch

Load, haul, roll and set — seemingly simple words unless associated with a 555,000-pound, 160-foot long, 18-foot wide, over 19-foot tall refinery combination tower.

Many Lifts, One Solution: Modular Lift System Flexes Hydraulic Muscles During Process Plant Overhaul

View Project
Many Lifts, One Solution: Modular Lift System Flexes Hydraulic Muscles During Process Plant Overhaul

Deep South crews were challenged to haul, lift, and set 84 modules, including three towers (one measuring 100’ long, 350,000 lbs.) as well as various pieces of process equipment, such as piping, tanks, PDC buildings, and transformers—all within a tight schedule. Many of the modules had offset centers of gravity further complicating the lift and set.

Deep South Crane

Dismantling and Relocating A Petrochemical Facility

View Project
Dismantling and Relocating A Petrochemical Facility

Deep South was contracted to dismantle and relocate 9 vessels from a petrochemical plant using a combination of barging, heavy transport, and heavy lift services.

A Marathon Job, Literally

View Project
A Marathon Job, Literally

As seen in American Cranes and Transport Magazine

Transforming a 200-acre sugarcane field in Garyville, LA into a state-of-the-art refinery required a $3.8 billion investment and the work of a cadre of contractors with expertise that spanned the entire spectrum of engineering, construction, and rigging. Construction on the Marathon GME project started in March of 2007, and by December of 2009 the refinery was mechanically complete.

A successful job is built on precise planning and safe execution. request a quote