Throughout our nearly five decades of experience in heavy lift and transport solutions, we have learned that a successful job is built on precise planning and safe execution. This mindset has allowed our business to grow and positively impact some of the most complex projects across two continents. Take a look at what we can do.
- Projects Filtered by:
- CC-1400
- Clear Filters
Turnaround Efficiency: Lift, Lower and Slide
View Project
Turnaround Efficiency: Lift, Lower and Slide
A major process unit turnaround (TAR) project for a petrochemical plant in the Southwest required some well-planned logistics, over 1,200 craftworkers (at peak) and a comprehensive fleet of cranes, trucks and customized skid (Jack & Slide) systems.
Coker Derrick Structure Installation
View Project
Coker Derrick Structure Installation
Deep South hoisted and set the four sections of the coker derrick structure, the heaviest of which weighed 256 tons, and two 450-ton coke drums at a Midwest Refinery using our 2,500-ton VersaCrane TC-36000 and our 275-ton Demag CC-1400.
A Marathon Job, Literally
View Project
A Marathon Job, Literally
As seen in American Cranes and Transport Magazine
Transforming a 200-acre sugarcane field in Garyville, LA into a state-of-the-art refinery required a $3.8 billion investment and the work of a cadre of contractors with expertise that spanned the entire spectrum of engineering, construction, and rigging. Construction on the Marathon GME project started in March of 2007, and by December of 2009 the refinery was mechanically complete.