News


Mitigating the Mississippi - A Case Study

Terex CC-6800-1 Crane Deep South

THE CHALLENGE:

To barge, transport, and stage two exchangers while the Mississippi River was at a historic low and Corps requirements continued to change. In addition, low-lying pipe racks and tight quarters hindered transportation and lifting of the exchangers to their final destination.

THE DETAILS:

When the owner was ready to install new exchangers in its styrene monomer production facility, the company turned to Deep South Crane & Rigging. Positioning the exchangers, weighing 300T and 120T respectively, required agile maneuvering of the equipment under a pipe rack with less than a two-inch clearance and throughout the remainder of the plant. Deep South is one of the few firms with such capability, with the added benefit of its new Terex CC6800-1 crane not encroaching on work elsewhere in the plant. "This was a very specialized transportation and lift job. We had the best technical solution for getting under their pipe rack, and the crane selection was such that it didn't disrupt other areas of their plant," says Deep South project manager Thad Lentz. After months of planning, a more arduous challenge arose: The Mississippi River itself.

When it came time to receive the exchangers barge at the port, the Carrollton gauge in New Orleans registered the river's depth at one foot a historic low far below the 7- to 11-foot norm. The U.S. Army Corps of Engineers wouldn't grant a permit to offload the exchangers under those conditions, and the river wasn't expected to rise anytime soon. "Getting a permit isn't as difficult when the river is a normal level, Lentz says. "But when it dropped down to one foot, the Army Corps of Engineers told us, You are not offloading. Period. That wasn't an option for us. And it wasn't an option for our client. They had to complete their turnaround, and they had to have that exchanger.

The company conducted a new stability analysis of the levee and designed a solution to safely offload the equipment, meet the Corps requirements and secure the permit as quickly as possible. Deep South installed 2,000 feet of reinforcement mats along the entire levee. The team then assembled a customized ramp, which was designed and built at its fabrication facility in Baton Rouge, to reach the barge. The permit to offload in low water was granted in mid-January of 2013, delaying the owner's turnaround by just two weeks. The exchangers were in place in 20 days. Working with the Army Corps of Engineers and its client to provide solutions around continuously changing river levels is part of Deep South's expertise. Its team overcame the challenge, minimizing months of potential delays for the client.

Heavy Transport Project Deep South Crane

A High Pressure Exchange

Assembling the 1,500T VersaCrane™ TC-24000 off site and moving it via SPMT saved this client 15 days of downtime and allowed the refinery unit to run at full capacity until unit shutdown. During the scheduled outage, Deep South was tasked to replace two coke drums, each weighed 452,800 lbs and were 19’-2” outside diameter and 96’-0” long and were comparable in size and weight to the old drums.

READ MORE

Safety Source: OSHA's Safe + Sound Week

The Occupational Safety & Health Administration's Safe + Sound Week is a nationwide event to recognize the successes of businesses that have adopted programs to improve workplace safety and health. This year's Safe + Sound Week ​will be held August 12-18, 2024, and focus on Job Hazard Analysis (JHAs). Deep South is pleased to participate in this annual event again.

READ MORE


A successful job is built on precise planning and safe execution. request a quote