Turnkey Demolition Facilitates Clean Refinery Modernization
The Reficar refinery, first constructed in 1956 in Cartagena, Columbia, was undergoing a clean energy modernization and expansion to more than double its capacity 80,000 barrels per day (bpd) to 165,000 bpd. The refinery is owned and operated by Refinería de Cartagena (REFICAR), an affiliate of Ecopetrol. The overall project includes the construction of a new refinery adjacent to REFICAR's refinery in Cartagena; revamping the existing 80,000 barrel per day refinery; and relief of the regional refining constraints that will enable REFICAR to produce clean, ultra-low sulfur gasoline and diesel from heavy crude.
REFICAR contracted Deep South to complete the safe removal, demolition, and transport of old systems in parallel with the modernization effort. The removal and demolition included a fluid catalytic cracking (FCC) unit, air blower unit, much of the polymerization unit as well as a range of exchangers, and other related systems.
“The demolition of an over 50-year-old plant on a time sensitive schedule required considerable planning and reliable, versatile equipment,” explains Fernando Gonzalez, project engineer with Deep South Crane. “The systems were large, heavy, dirty, and rusty. Every major component had to be broken down into transportable pieces. As always, crew safety was our first priority.”
The FCC unit proved particularly challenging as the complete unit was nearly 200 feet tall, 70 feet wide, and had a total equipment weight of approximately 2,170,000 pounds. Crews cut the reactor into multiple sections and then used Deep South’s patented VersaCrane™ TC-24000, a 1,500-ton compact crane designed for heavy lifts crowded and congested areas, to transport the pieces to the nearby laydown yard.
Over the course of 8 months, Deep South’s crews and local labor performed more than 100 lifts, 50 of which were critical, with the TC-24000 and other cranes including the 750-ton VersaCrane CC-9600 and the 330-ton Demag CC-1800 crawler crane.
The facility equipment removed ranged from exchangers as small as 5,000 pounds to the largest part of the reactor weighing approximately 250,000 pounds.
The Reficar refinery expansion project was commissioned in 2015.
-
Equipment Used
-
Services Used
-
By the Numbers
- Demolished and Removed 3 Units
- 50 Critical Lifts
- 100+ Total Lifts
- Weights Lifted Ranged From 5,000 - 250,000 pounds
Related Projects
Super-Sized Truss No Problem for High Capacity Crane
View Project
Super-Sized Truss No Problem for High Capacity Crane
Deep South lifted and set double-rail bridge truss sections weighing 800,000 pounds each along a railroad line that crosses the Tug Fork River at Hatfield Bottom near Matewan, WV. Our crews engineered and fabricated custom lifting beams suitable for removing the existing truss bridges and lifting the new bridge spans into place and used our 1,760-ton capacity Terex-Demag CC-8800-1 crawler crane.
124-line SPMT Chemical Reactor Transport
View Project
124-line SPMT Chemical Reactor Transport
In the Southwest, Deep South received three vessels from a heavy lift ship at the Port of Houston, barged the vessels, and transported them to final staging using a total of 124-axle lines Scheuerle SPMT. The heaviest vessel weighed 1,800,000 pounds and the total gross weight at transport for that vessel was 2,300,000 pounds.
Industrial Airpark Lift
View Project
Industrial Airpark Lift
At an industrial airpark in Louisiana, Deep South set steel roof sections weighing 32,000 pounds and measuring 85' long by 30' wide each.