The upper and lower sections of this vessel, weighing 85T and 102T, were transported from the port to the refinery using dual lane Goldhofers.
In South America, Deep South demolished and removed three units within a petrochemical facility that was more than 50 years old.
Deep South loaded, secured, and transported four pressure vessels from a fabrication shop to a petrochemical facility using a combination of Scheuerle SPMTs, a 500-ton hydraulic gantry, and Goldhofer Dual Lane trailers.