Deep South hoisted and set the four sections of the coker derrick structure, the heaviest of which weighed 256 tons, and two 450-ton coke drums at a Midwest Refinery using our 2,500-ton VersaCrane TC-36000 and our 275-ton Demag CC-1400.
Supplying all cranes in two units during a petrochemical turnaround in the Southeast, Deep South supported the change out of old components and reinstallation of new components with 19 cranes working throughout the project.
Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system and then trans-loaded onto Scheuerle SPMTs in a very congested unit.