Tight Tailswing, Turnkey Solution
In the Southeast, Deep South performed a complex turnkey project that required equipment modification and careful planning.
To begin, Deep South received a reactor from the ship of origin and transported it via barge to a petrochemical facility up river. Using Goldhofer SPMTs, Deep South off-loaded the vessel from the barge and negotiated very tight turns and low pipe racks with minimum clearance to get it to the final off-loading location. Five-hundred-ton gantries were used to off-load to temporary supports.
Deep South modified the 1,500-ton VersaCrane TC-24000 specifically for this project to accommodate a very tight tail swing requirement. The vessel weighed 420,000 pounds, measured 100’ long and was lifted using 200’ of boom at a 95’ radius. Scheuerle SPMTs were used with the tailing frame to tail the load due to space constraints.
-
Equipment Used
-
Services Used
-
By the Numbers
- Vessel Weighed 420,000 Pounds
- Vessel Measured 100’ Long
- VersaCrane was 200’ of Boom at a 95’ Radius
Related Projects
Cantilever Bar Approach Helps Ease Exchangers Into Place
View Project
Cantilever Bar Approach Helps Ease Exchangers Into Place
Deep South used a cantilever beam (also commonly referred to as a cantilever bar), which incorporates a compact counterweight design with customizable rigging attachment points, to move eight 118,000-pound exchangers into position under an existing steel structure at a refinery optimization project in the Southwest.
Scheuerles Haul 750 Ton Tugboat
View Project
Scheuerles Haul 750 Ton Tugboat
Deep South was contracted to transport a 750-ton tugboat.
400,400 Pound Boiler Lifts
View Project
400,400 Pound Boiler Lifts
Three boilers were delivered horizontally to Deep South’s 500-ton hydraulic gantry system and then trans-loaded onto Scheuerle SPMTs in a very congested unit.