200 Lifts at Michigan Power Plant
At a Michigan power plant, Deep South utilized a 660-ton Demag CC-2800 (pictured here) to complete 200 lifts over an 8 month duration. This included multiple bag-house modules and duct sections, weighing up to 85 tons and measuring up to 85 feet in length. In addition, the 160-ton Tadano GR-1600XL-2 was used in the early phase of the project for erecting steel. Extreme temperatures brought 100 inches of snow during this time.
-
Equipment Used
-
Services Used
-
By the Numbers
- 200 Lifts
- Weighing up to 85 Tons
- Measuring up to 85' in Length
- 100" of Snow
Related Projects
Transporters and Cranes Facilitate Processing Plant Upgrade
View Project
Transporters and Cranes Facilitate Processing Plant Upgrade
The movement and replacement of process plant components are a familiar site in in the Texas Gulf Coast region—though not often to the scale and timeline faced by one EPC contractor. Per the client, the contractor was tasked with the haul and lift of two trains of fractionation tower components (debutanizer, depropanizer, splitter and deethanizer) over the course of nine months.
Creative Thinking Keeps Transport Costs Low and Delivery Quick
View Project
Creative Thinking Keeps Transport Costs Low and Delivery Quick
As part of a natural gas fractionation project, an EPC contractor needed to transport two large drums to the customer’s facility.
15 Module Lift and Transport
View Project
15 Module Lift and Transport
Deep South was contracted by a Gulf Coast refinery to transport fifteen modules from a fabrication shop in Port Allen, LA to the site in Norco, LA.