200 Lifts at Michigan Power Plant
At a Michigan power plant, Deep South utilized a 660-ton Demag CC-2800 (pictured here) to complete 200 lifts over an 8 month duration. This included multiple bag-house modules and duct sections, weighing up to 85 tons and measuring up to 85 feet in length. In addition, the 160-ton Tadano GR-1600XL-2 was used in the early phase of the project for erecting steel. Extreme temperatures brought 100 inches of snow during this time.
-
Equipment Used
-
Services Used
-
By the Numbers
- 200 Lifts
- Weighing up to 85 Tons
- Measuring up to 85' in Length
- 100" of Snow
Related Projects
Turnkey in Tight Quarters: Split Trailers Reduce Height with Inches to Spare
View Project
Turnkey in Tight Quarters: Split Trailers Reduce Height with Inches to Spare
For a refinery in the Southeast, Deep South was contracted to remove and replace a derrick structure and two 491,000-pound vessels, each measuring 99’ long and 24’2” diameter.
Caustic & PreFrac Tower Lift
View Project
Caustic & PreFrac Tower Lift
Deep South Crane and Rigging was recently contracted by a southeast petrochemical plant as part of a major pre-turnaround project. In order to de-bottleneck ethylene production, Deep South erected a caustic tower and a prefrac tower.
300T Offshore Living Quarters Lift
View Project
300T Offshore Living Quarters Lift
This 300T living quarters module was installed onto an offshore support ship using the Terex Demag CC-2800.